| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA APA EST | Suministro y colocacion de cimbra acabado aparente en estructura principal, (columnas,trabes y losas) | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 2.960000 | $5.61 | $16.61 |
| MADERA POLIN | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 4.920000 | $6.50 | $31.98 |
| MADERA-6 | CIMBRAPLAY 16 MM HOJA DE 1.22 X 2.44 | M2 | 0.250000 | $92.00 | $23.00 |
| MADERA CHAFLAN | CHAFLAN 1" | ml | 1.900000 | $3.20 | $6.08 |
| CLAVO (VARIAS MED.) | CLAVO PARA MADERA VARIAS MEDIDAS | KG | 0.250000 | $17.00 | $4.25 |
| ALAMBRE REC | ALAMBRE RECOCIDO | KG | 0.233000 | $14.87 | $3.46 |
| ACERO NO. 2 | Acero de refuerzo núm. 2 (1/4" ) fyp = 2530 kg/ml | KG | 0.233000 | $13.45 | $3.13 |
| DIESEL | DIESEL | LT | 0.600000 | $4.71 | $2.83 |
| Suma de Material | $91.34 | ||||
| Mano de Obra | |||||
| CUAD OC 07 | CUAD. 1 CARPINTERO DE OBRA NEGRA + 1 AYTE. | JOR | 0.104710 | $1,105.17 | $115.72 |
| Suma de Mano de Obra | $115.72 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR. | HERRAMIENTA MENOR | (%)mo | 0.030000 | $115.72 | $3.47 |
| EQUIPO DE SEGURIDAD | Equipo de Primera Seguridad (Casco, Botas, Guantes, Gafas, Chaleco Preventivo) | (%)mo | 0.030000 | $115.72 | $3.47 |
| Suma de Herramienta | $6.94 | ||||
| Costo Directo | $214.00 |