| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| BAS11/2" | SUMINISTRO Y EXTRACCION DE MATERIAL PETREO DE 1 1/2" A FINOS | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| REGA1 | REGALIAS DE MATERIAL | M3 | 1.000000 | $20.00 | $20.00 |
| Suma de Material | $20.00 | ||||
| Equipo | |||||
| EQ00001 | TRITURADORA DE CONO NORDBERG-SYMONS DE 150 HP. Y MALLAS MOD.200 | hora | 0.038000 | $536.39 | $20.38 |
| EQ000030 | EXCAVADORA 320 ( 160 HP) CATERPILLAR | hora | 0.010000 | $474.05 | $4.74 |
| EQ01, | TRACTOR D-8 K DE 285 H.P. CATERPILLAR | hora | 0.010000 | $584.91 | $5.85 |
| EQL | PLANTA DE LUZ 340-B DIESEL DE 65 HP CATERPILLAR | hora | 0.010000 | $266.92 | $2.67 |
| EQUI001 | QUEBRADORA DEQUIJADAS NORDBERG-SYMONS T560 130 HP MOD:2000 | hora | 0.035000 | $671.10 | $23.49 |
| EQAR | CAMION ARTICULADO MCA. DJB 250 HP MOD:2000 | hora | 0.008000 | $474.78 | $3.80 |
| Suma de Equipo | $60.93 | ||||
| Costo Directo | $80.93 |