| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IV.003-TA3 | SUMINISTRO Y FABRICACION Y COLOCACION DE TAPA DE 1.40 X 1.40 M., DE CONCRETO F'C=200KG/CM2, REF. CON VAR. No. 3, CON MARCO Y CONTRAMARCO METALICO | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE F-C 200 | concreto prmezclado de f´c = 200 kg / cm2 en cimentacion | m3 | 0.083000 | $703.00 | $58.35 |
| MADERA DE PINO DE 3A | MADERA DE PINO DE 3a. | PT | 0.900000 | $9.12 | $8.21 |
| CLAVO CON CABEZA DE | Clavo con cabeza de 3" .004KG/PZA PROM. | kg | 0.120000 | $16.12 | $1.93 |
| OXIGENO | OXIGENO | M3 | 0.040000 | $235.00 | $9.40 |
| GAS | GAS P/ CORTES | kg | 0.200000 | $6.50 | $1.30 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.080000 | $29.69 | $2.38 |
| PRIMARIO ANTICORROSI | PRIMARIO ANTICORROSIVO | LT | 0.300000 | $56.00 | $16.80 |
| THINER | THINER | lt | 0.300000 | $12.00 | $3.60 |
| ACERO | ACERO REF.VAR.DIAM. | kg | 6.000000 | $9.50 | $57.00 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.200000 | $10.12 | $2.02 |
| ANGULO METALICO1 | ANGULO METALICO ESTRUCTURAL | KG | 59.410000 | $11.00 | $653.51 |
| SOLDADURA | SOLDADURA DE ELECTRODOS | KG | 0.600000 | $35.00 | $21.00 |
| Suma de Material | $835.50 | ||||
| Mano de Obra | |||||
| CUADRILLA -52 | (1 SOLDADOR + 1 AYUDANTE) | JOR | 0.200000 | $933.26 | $186.65 |
| CUADRILLA -02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.115000 | $772.60 | $88.85 |
| Suma de Mano de Obra | $275.50 | ||||
| Equipo | |||||
| SOLDADORA EST. | Soldadora Miller Dimension Mod. 652 | HR | 0.700000 | $31.60 | $22.12 |
| EQUIPO DE OXICORTE | EQUIPO DE OXICORTE | hora | 0.500000 | $11.79 | $5.90 |
| ESMERILADORA | ESMERILADORA | HR | 0.600000 | $5.59 | $3.35 |
| Suma de Equipo | $31.37 | ||||
| Costo Directo | $1,142.37 |