| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3.01.02.026-H.10 | CONCRETO HIDRAULICO DE F'C=150 KG/CM2 EN ( 047-G.11.A.1 ) | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-01 | premezclado f`c=150 kg/cm2 | m3 | 1.050000 | $665.00 | $698.25 |
| CONCRETO PRE-01 | premezclado f`c=150 kg/cm2 | m3 | 1.050000 | $665.00 | $698.25 |
| CIMBRA-04 | MADERA DE PINO | PT | 8.130000 | $8.00 | $65.04 |
| CIMBRA-04 | MADERA DE PINO | PT | 8.130000 | $8.00 | $65.04 |
| CIMBRA-01 | CIMBRAPLAY | M2 | 1.350000 | $69.00 | $93.15 |
| CIMBRA-01 | CIMBRAPLAY | M2 | 1.350000 | $69.00 | $93.15 |
| CIMBRA-02 | CLAVO | Kg. | 2.363636 | $19.13 | $45.22 |
| CIMBRA-02 | CLAVO | Kg. | 2.363636 | $19.13 | $45.22 |
| CONCRETO PRE-03 | BOMBA PARA CONCRETO | M3 | 1.000000 | $100.00 | $100.00 |
| CONCRETO PRE-03 | BOMBA PARA CONCRETO | M3 | 1.000000 | $100.00 | $100.00 |
| Suma de Material | $2,003.31 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.150000 | $491.76 | $73.76 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.150000 | $491.76 | $73.76 |
| Suma de Mano de Obra | $147.53 | ||||
| Equipo | |||||
| MAQUINARIA-23 | VIBRADOR PARA CONCRETO MOD MVK4-AA3614 CON MOTOR KOHLER DE 4 HP Y CONJUNTO CABEZAL DE 4.20 MTS. | HR | 0.500000 | $12.67 | $6.34 |
| MAQUINARIA-23 | VIBRADOR PARA CONCRETO MOD MVK4-AA3614 CON MOTOR KOHLER DE 4 HP Y CONJUNTO CABEZAL DE 4.20 MTS. | HR | 0.500000 | $12.67 | $6.34 |
| Suma de Equipo | $12.67 | ||||
| Costo Directo | $2,163.51 |