| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| AA-019 | SUMINISTRO COLOCACION, JUNTEO Y PRUEBA DE TUBERIA DE PVC RD-32.5 C/CAMPANA, DE 3" DE DIAM.,INCLUYE; ANILLO DE HULE Y HERRAMIENTA MENOR. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.029500 | $23.00 | $0.68 |
| TUBO PVC HID 3" | TUBERIA DE PVC HIDRAULICO RD-32.5 DE 3" DE DIAM. | ml | 1.050000 | $31.05 | $32.60 |
| Suma de Material | $33.28 | ||||
| Mano de Obra | |||||
| MO-027 | TUBERO DE 1ª. | jor | 0.035710 | $330.30 | $11.80 |
| AYUDANTE | AYUDANTE. | JOR | 0.035710 | $199.89 | $7.14 |
| CABO | CABO DE CUADRILLA | Jor. | 0.003570 | $412.60 | $1.47 |
| Suma de Mano de Obra | $20.41 | ||||
| Herramienta | |||||
| HERRAM | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $53.69 |