| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| AA-002 | SUMINISTRO COLOCACION, JUNTEO Y PRUEBA DE TUBERIA DE ASBESTO CEMENTO CLASE A-5, DE 8" DE DIAM. | ML. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO A.C. A-5, 8" | TUBO DE ASBESTO CEMENTO CLASE A-5 DE 8" DE DIAM. | ml | 1.050000 | $85.00 | $89.25 |
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.040300 | $23.00 | $0.93 |
| Suma de Material | $90.18 | ||||
| Mano de Obra | |||||
| MO-027 | TUBERO DE 1ª. | jor | 0.018200 | $330.30 | $6.01 |
| MO-028 | TUBERO DE 2ª. | jor | 0.018200 | $263.56 | $4.80 |
| AYUDANTE | AYUDANTE. | JOR | 0.018200 | $199.89 | $3.64 |
| CABO | CABO DE CUADRILLA | Jor. | 0.002730 | $412.60 | $1.13 |
| Suma de Mano de Obra | $15.57 | ||||
| Herramienta | |||||
| HERRAM | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $105.75 |