| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PAV-004 | GUARNICION DE CONCRETO SIMPLE F'C=150 KG/CM2, 12-17x40 CM. DE SECCION, CIMBRA METALICA. | ML. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.006500 | $23.00 | $0.15 |
| Suma de Material | $0.15 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADR. No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.041670 | $478.34 | $19.93 |
| Suma de Mano de Obra | $19.93 | ||||
| Auxiliar | |||||
| CIM-GUARN | CIMBRA PARA GUARNICON DE 15x30 CM. | M2 | 0.800000 | $91.28 | $73.02 |
| BA4 | CONCRETO HECHO EN OBRA, FC'= 150 KG./CM2. T.M.A. 3/4" | M3. | 0.063000 | $942.52 | $59.38 |
| Suma de Auxiliar | $132.40 | ||||
| Costo Directo | $152.48 |