| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PRE-TZD | TRAZO Y NIVELACION CON EQUIPO TOPOGRAFICO EN AREAS DE REMODELACION, ESTABLECIENDO EJES DE REFERENCIA Y BANCOS DE NIVEL. INCLUYE: MATERIALES, DESPERDICIOS, MANO DE OBRA, EQUIPO Y HERRAMIENTA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGL-002 | CALHIDRA. | ton | 0.000300 | $1,694.61 | $0.51 |
| MAD-002 | MADERA DE PINO DE 3a. EN BARROTES DE 2" x 4" | P.T. | 0.045200 | $14.11 | $0.64 |
| MAD-11 | CARRETE DE HILO DE PLASTICO | PZA | 0.009000 | $25.41 | $0.23 |
| Suma de Material | $1.37 | ||||
| Mano de Obra | |||||
| CUAD-TOP | CUADRILLA DE TOPOGRAFIA | JOR | 0.015000 | $1,072.74 | $16.09 |
| Suma de Mano de Obra | $16.09 | ||||
| Equipo | |||||
| MAQ-C-1 | TRANSITO K-E MOD. K5 | HOR | 0.064000 | $5.67 | $0.36 |
| MAQ-C-2 | NIVEL K-E MOD 510 | HOR | 0.060000 | $7.10 | $0.43 |
| H | % HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| H2 | % EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Equipo | $0.79 | ||||
| Costo Directo | $18.25 |