| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| LUMM08 | BASE PIRAMIDAL TRUNCADA PARA POSTE DE LUMINARIO, CON LAS SIGUIENTES DIMENSIONES: BASE MENOR DE 30 X 30 cm., BASE MAYOR DE 80 X 80 cm., PERALTE DE 80 cm., CONCRETO F'c = 200 Kg/cm2, ARMADO CON 4 VARILLAS DEL NO 3 (3/8"), ESTRIBOS DEL NO 2 A/C 30 cm., SEGÚN MARCA PROYECTO, INCLUYE: 4 ANCLAS DE 5/8" DE DIÁMETRO X 50 cm. DE LARGO, SUMINISTRO E INSTALACIÓN DE LOS MATERIALES, HERRAMIENTAS, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA CONSTRUCCIÓN. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ADT-CONC-01 | MEMBRANA DE CURADO CURACRETO | LT | 0.430000 | $25.00 | $10.75 |
| ACE-3 | ACERO DE REFUERZO A.R. VARILLA F´y =4200 KG/CM2 No. 3. | TON | 0.002450 | $14,448.00 | $35.40 |
| VAR-002 | ACERO DE REFUERZO DEL No. 02 (1/4" ) ALAMBRON | Kg | 1.647000 | $15.97 | $26.30 |
| ANC-5/8 | ANCLA DE 5/8" | PZA | 4.000000 | $130.95 | $523.80 |
| ALAMBRE-001 | ALAMBRE DE RECOCIDO, CAL. 18. | Kg | 0.100000 | $15.43 | $1.54 |
| Suma de Material | $597.79 | ||||
| Mano de Obra | |||||
| CUAD-001-01 | CUADRILLA No. 001 ( PEON ) | JOR | 1.200000 | $359.56 | $431.47 |
| CUAD-0010-01 | CUADRILLA No. 0010 ( 1 OF. ALBAÑIL + 1 AYUDANTE ) | JOR | 1.100000 | $874.31 | $961.74 |
| CUAD-00001011 | CUADRILLA (1 OFICIAL FIERRERO + 1 AYUDANTE GENERAL) | JOR | 0.070000 | $839.69 | $58.78 |
| Suma de Mano de Obra | $1,451.99 | ||||
| Equipo | |||||
| MAQ-513 | VIBRADOR PARA CONCRETO, MARCA DYNAPAC, MODELO MV-K8, MOTOR DE GASOLINA DE 8 H.P. | Hora | 0.500000 | $21.27 | $10.64 |
| MAQ-108 | REVOLVEDORA PARA CONCRETO, MARCA MIPSA, MODELO 6S-R-10, MOTOR GASOLINA DE 8 H.P., CAPACIDAD 1 SACO. | Hora | 0.800000 | $49.12 | $39.30 |
| H | % HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| H2 | % EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Equipo | $49.93 | ||||
| Auxiliar | |||||
| CONC-200-0 | CONCRETO HIDRAULICO DE RESISTENCIA F'C= 200 KG/CM2 AGR. MAXIMO 19 MM | M3 | 0.320000 | $1,242.38 | $397.56 |
| CIM-001-0 | CIMBRA DE MADERA COMUN | M2 | 0.840000 | $115.07 | $96.66 |
| Suma de Auxiliar | $494.22 | ||||
| Costo Directo | $2,593.94 |