| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ESOP-100 | SOPORTE PARA TUBERÍAS CONDUIT GALVANIZADAS, COMPRENDE: PERNOANCLA ROSCADO DE 1/4" DE DIÁMETRO, CAT. 191-W62027-12, MARCA TAMEX; COPLE HEXAGONAL DE 1/4" DE DIÁMETRO, MARCA TAMEX; VARILLA ROSCADA DE 1/4" DE DIÁMETRO, ANILLO FORJADO AJUSTABLE MARCA TAMEX, INCLUYE: SUMINISTRO E INSTALACIÓN DE LOS MATERIALES, ANDAMIOS, HERRAMIENTAS Y TODO LO NECESARIO PARA SU CORRECTA COLOCACIÓN Y FUNCIONAMIENTO. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SOPT10 | PERNOANCLA ROSCADO DE 1/4" DE DIÁMETRO, CAT. 191-W62027-12, MARCA TAMEX | PZA | 1.000000 | $20.18 | $20.18 |
| SOPT10 | PERNOANCLA ROSCADO DE 1/4" DE DIÁMETRO, CAT. 191-W62027-12, MARCA TAMEX | PZA | 1.000000 | $20.18 | $20.18 |
| SOPT10 | PERNOANCLA ROSCADO DE 1/4" DE DIÁMETRO, CAT. 191-W62027-12, MARCA TAMEX | PZA | 1.000000 | $20.18 | $20.18 |
| SOPT11 | COPLE HEXAGONAL DE 1/4" DE DIÁMETRO, MARCA TAMEX | PZA | 1.000000 | $1.75 | $1.75 |
| SOPT11 | COPLE HEXAGONAL DE 1/4" DE DIÁMETRO, MARCA TAMEX | PZA | 1.000000 | $1.75 | $1.75 |
| SOPT11 | COPLE HEXAGONAL DE 1/4" DE DIÁMETRO, MARCA TAMEX | PZA | 1.000000 | $1.75 | $1.75 |
| SOPT03 | VARILLA ROSCADA DE 1/4" | PZA | 1.000000 | $15.14 | $15.14 |
| SOPT03 | VARILLA ROSCADA DE 1/4" | PZA | 1.000000 | $15.14 | $15.14 |
| SOPT03 | VARILLA ROSCADA DE 1/4" | PZA | 1.000000 | $15.14 | $15.14 |
| SOPT12 | ANILLO FORJADO AJUSTABLE MARCA TAMEX | PZA | 1.000000 | $10.92 | $10.92 |
| SOPT12 | ANILLO FORJADO AJUSTABLE MARCA TAMEX | PZA | 1.000000 | $10.92 | $10.92 |
| SOPT12 | ANILLO FORJADO AJUSTABLE MARCA TAMEX | PZA | 1.000000 | $10.92 | $10.92 |
| Suma de Material | $143.97 | ||||
| Mano de Obra | |||||
| CUAD-1130-02 | CUADRILLA No. 1130 ( 1 TEC. ELECTRICISTA + 1 AYUDANTE ) | JOR | 0.080000 | $901.12 | $72.09 |
| CUAD-1130-02 | CUADRILLA No. 1130 ( 1 TEC. ELECTRICISTA + 1 AYUDANTE ) | JOR | 0.080000 | $901.12 | $72.09 |
| CUAD-1130-02 | CUADRILLA No. 1130 ( 1 TEC. ELECTRICISTA + 1 AYUDANTE ) | JOR | 0.080000 | $901.12 | $72.09 |
| Suma de Mano de Obra | $216.27 | ||||
| Equipo | |||||
| EQUIPO-001 | ANDAMIOS TUBULARES | Hora | 0.100000 | $6.78 | $0.68 |
| EQUIPO-001 | ANDAMIOS TUBULARES | Hora | 0.100000 | $6.78 | $0.68 |
| EQUIPO-001 | ANDAMIOS TUBULARES | Hora | 0.100000 | $6.78 | $0.68 |
| H | % HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| H | % HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| H | % HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| H2 | % EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| H2 | % EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| H2 | % EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Equipo | $2.03 | ||||
| Costo Directo | $362.27 |