| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ECON-250/TRALO/10MTS | CONCRETO PREMEZCLADO EN TRABES, COLUMNAS Y LOSA, F'c = 250 Kg/cm2, RESISTENCIA NORMAL, VACIADO CON BOMBA, REVENIMIENTO DE 12 cm., AGREGADO MÁXIMO 3/4", HASTA UNA ALTURA MÁXIMA DE 10.00 mts., INCLUYE: NIVELADO SEGÚN INDICA PROYECTO, PRUEBAS DE LABORATORIO, MATERIALES, DESPERDICIOS, MANO DE OBRA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONPRE250 | CONCRETO PREMEZCLADO F´C= 250 KG/CM2, CON CEMENTO GRIS . agregado max. 19 mm. INCLUYE BOMBEADO. | M3 | 1.030000 | $1,855.20 | $1,910.86 |
| CONPRE250 | CONCRETO PREMEZCLADO F´C= 250 KG/CM2, CON CEMENTO GRIS . agregado max. 19 mm. INCLUYE BOMBEADO. | M3 | 1.030000 | $1,855.20 | $1,910.86 |
| CONPRE250 | CONCRETO PREMEZCLADO F´C= 250 KG/CM2, CON CEMENTO GRIS . agregado max. 19 mm. INCLUYE BOMBEADO. | M3 | 1.030000 | $1,855.20 | $1,910.86 |
| PBA-1 | PRUEBAS DE CONTROL DE CALIDAD PARA DETERMINAR LA RESISTENCIA DEL CONCRETO. | PZA | 0.166667 | $206.00 | $34.33 |
| PBA-1 | PRUEBAS DE CONTROL DE CALIDAD PARA DETERMINAR LA RESISTENCIA DEL CONCRETO. | PZA | 0.166667 | $206.00 | $34.33 |
| PBA-1 | PRUEBAS DE CONTROL DE CALIDAD PARA DETERMINAR LA RESISTENCIA DEL CONCRETO. | PZA | 0.166667 | $206.00 | $34.33 |
| ADT-CONC-01 | MEMBRANA DE CURADO CURACRETO | LT | 0.435000 | $25.00 | $10.88 |
| ADT-CONC-01 | MEMBRANA DE CURADO CURACRETO | LT | 0.435000 | $25.00 | $10.88 |
| ADT-CONC-01 | MEMBRANA DE CURADO CURACRETO | LT | 0.435000 | $25.00 | $10.88 |
| Suma de Material | $5,868.19 | ||||
| Mano de Obra | |||||
| CUAD-001-04 | CUADRILLA No. 004 (4 PEONES ) | JOR | 0.026000 | $1,438.25 | $37.39 |
| CUAD-001-04 | CUADRILLA No. 004 (4 PEONES ) | JOR | 0.026000 | $1,438.25 | $37.39 |
| CUAD-001-04 | CUADRILLA No. 004 (4 PEONES ) | JOR | 0.026000 | $1,438.25 | $37.39 |
| CUAD-0010-01 | CUADRILLA No. 0010 ( 1 OF. ALBAÑIL + 1 AYUDANTE ) | JOR | 0.036000 | $874.31 | $31.48 |
| CUAD-0010-01 | CUADRILLA No. 0010 ( 1 OF. ALBAÑIL + 1 AYUDANTE ) | JOR | 0.036000 | $874.31 | $31.48 |
| CUAD-0010-01 | CUADRILLA No. 0010 ( 1 OF. ALBAÑIL + 1 AYUDANTE ) | JOR | 0.036000 | $874.31 | $31.48 |
| Suma de Mano de Obra | $206.61 | ||||
| Equipo | |||||
| EQUIPO-001 | ANDAMIOS TUBULARES | Hora | 0.260000 | $6.78 | $1.76 |
| EQUIPO-001 | ANDAMIOS TUBULARES | Hora | 0.260000 | $6.78 | $1.76 |
| EQUIPO-001 | ANDAMIOS TUBULARES | Hora | 0.260000 | $6.78 | $1.76 |
| MAQ-513 | VIBRADOR PARA CONCRETO, MARCA DYNAPAC, MODELO MV-K8, MOTOR DE GASOLINA DE 8 H.P. | Hora | 0.010000 | $21.27 | $0.21 |
| MAQ-513 | VIBRADOR PARA CONCRETO, MARCA DYNAPAC, MODELO MV-K8, MOTOR DE GASOLINA DE 8 H.P. | Hora | 0.010000 | $21.27 | $0.21 |
| MAQ-513 | VIBRADOR PARA CONCRETO, MARCA DYNAPAC, MODELO MV-K8, MOTOR DE GASOLINA DE 8 H.P. | Hora | 0.010000 | $21.27 | $0.21 |
| H | % HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| H | % HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| H | % HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| H2 | % EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| H2 | % EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| H2 | % EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Equipo | $5.93 | ||||
| Costo Directo | $6,080.73 |