| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EAR-007/10MTS | ACERO DE REFUERZO No. 6 DIÁMETRO 3/4", EN ESTRUCTURA (COLUMNAS, TRABES Y LOSAS DE ESCALERA ) RESISTENCIA NORMAL Fy = 4200 Kg/cm2, HASTA UNA ALTURA MÁXIMA DE 10.00 mts., EL PRECIO UNITARIO INCLUYE: PRUEBAS DE LABORATORIO, MATERIAL, ACARREO LIBRE A 20 mts., HERRAMIENTA, TRASLAPES, DOBLECES, ANCLAJES, GANCHOS, DESPERDICIOS, MANO DE OBRA Y DEMÁS CARGOS CORRESPONDIENTES | TON |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACE-6 | ACERO DE REFUERZO A.R. VARILLA F´C =4200 KG/CM2 No. 6. | TON | 1.030000 | $14,672.00 | $15,112.16 |
| ACE-6 | ACERO DE REFUERZO A.R. VARILLA F´C =4200 KG/CM2 No. 6. | TON | 1.030000 | $14,672.00 | $15,112.16 |
| ALAMBRE-001 | ALAMBRE DE RECOCIDO, CAL. 18. | Kg | 26.200000 | $15.43 | $404.27 |
| ALAMBRE-001 | ALAMBRE DE RECOCIDO, CAL. 18. | Kg | 26.200000 | $15.43 | $404.27 |
| Suma de Material | $31,032.85 | ||||
| Mano de Obra | |||||
| CUAD-00001011 | CUADRILLA (1 OFICIAL FIERRERO + 1 AYUDANTE GENERAL) | JOR | 5.500000 | $839.69 | $4,618.30 |
| CUAD-00001011 | CUADRILLA (1 OFICIAL FIERRERO + 1 AYUDANTE GENERAL) | JOR | 5.500000 | $839.69 | $4,618.30 |
| Suma de Mano de Obra | $9,236.59 | ||||
| Equipo | |||||
| H | % HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| H | % HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| H2 | % EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| H2 | % EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Equipo | $0.00 | ||||
| Costo Directo | $40,269.44 |