| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| H-1 | GUARNICION DE CONCRETO F'C=200 KG/CM2, DE 15X20X40 CM. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 200 | CONCRETO PREMEZCLADO DE F?C=200 KG/CM2 | M3 | 0.077000 | $910.00 | $70.07 |
| CIMBRAPLAY 16 MM | CIMBRAPLAY 16MM | M2 | 0.200000 | $95.00 | $19.00 |
| MADERA DE PINO DE 3A | MADERA DE PINO DE 3a. | PT | 1.600000 | $7.50 | $12.00 |
| CLAVO DE 2 1/2" A 3 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.100000 | $13.00 | $1.30 |
| Suma de Material | $102.37 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | (1 Of. Albañil + 1 Peon) | jor | 0.066667 | $763.77 | $50.92 |
| Suma de Mano de Obra | $50.92 | ||||
| Equipo | |||||
| VIBRADORCONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.700000 | $21.44 | $15.01 |
| Suma de Equipo | $15.01 | ||||
| Costo Directo | $168.30 |