| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| B-9 | PRETIL DE CONCRETO F'C=200 KG/CM2, DE 15 CM. DE ESPESOR, DE HASTA 0.40 M. DE ALTURA, REFORZADO CON MALLA 6X6-6/6, PARA CONTENCION DE RELLENOS Y EN DESNIVELES DE PISO. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 200 | CONCRETO PREMEZCLADO DE F?C=200 KG/CM2 | M3 | 0.070000 | $910.00 | $63.70 |
| MALLA 6/6 6-6 | MALLA ELECTROSOLDADA 6X6/ 6-6 | M2 | 0.500000 | $18.43 | $9.22 |
| MADERA DE PINO DE 3A | MADERA DE PINO DE 3a. | PT | 3.600000 | $7.50 | $27.00 |
| CIMBRAPLAY 16 MM | CIMBRAPLAY 16MM | M2 | 0.220000 | $95.00 | $20.90 |
| MOÑOS | MOÑOS PARA CIMBRA | pieza | 1.500000 | $7.00 | $10.50 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.100000 | $12.00 | $1.20 |
| CLAVO DE 2 1/2" A 3 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.100000 | $13.00 | $1.30 |
| Suma de Material | $133.82 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | (1 Of. Albañil + 1 Peon) | jor | 0.100000 | $763.77 | $76.38 |
| CUAD OC 62 | (1 Of. Fierrero + 1 Ayud.) | jor | 0.050000 | $763.77 | $38.19 |
| CUAD OC 11 | (1 Of. Carpintero O.N. + 1 Ayud.) | jor | 0.200000 | $763.77 | $152.75 |
| Suma de Mano de Obra | $267.32 | ||||
| Costo Directo | $401.13 |