| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| B-3 | CASTILLO 15 X 20 CM. DE CONCRETO F'C=200KG/CM2, REFORZADA CON ARMEX. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.010000 | $12.00 | $0.12 |
| ARMEX 15X20-4 | ARMEX 15X20-4 | ML | 1.100000 | $14.00 | $15.40 |
| Suma de Material | $15.52 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | (1 Of. Albañil + 1 Peon) | jor | 0.110000 | $763.77 | $84.01 |
| Suma de Mano de Obra | $84.01 | ||||
| Auxiliar | |||||
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.030900 | $1,070.06 | $33.06 |
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Auxiliar | $33.06 | ||||
| Concepto | |||||
| 305 | SUMINISTRO Y HABILITADO DE CIMBRA APARENTE EN TRABES, Y CORNIZAS A BASE DE TRIPLAY DE PINO DE 16MM DE ESPESOR EN ESTRUCTURA (MAXIMO 4 USOS), INCLUYE OBRA FALSA, CHAFLANES, CONSUMIBLES, DESENCOFRANTE Y DESCIMBRA DE LOS ELEMENTOS, TODOS LOS MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO, ACARREOS HORIZONTALES Y VERTICALES, DESPERDICIOS Y TODO AQUELLO NECESARIO PARA LA CORRECTA Y COMPLETA EJECUCION DE ESTE CONCEPTO, INCLUYE ADEMAS LIMPIEZA DE OBRA Y RETIRO DE SOBRANTES FUERA DE LA OBRA. (P.U.O.T.) | M2 | 0.300000 | $151.89 | $45.57 |
| Suma de Concepto | $45.57 | ||||
| Costo Directo | $178.17 |