| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| E-1 | COLUMNA C-1 DE CONCRETO F'C=250KG/CM2, REF. CON 4 VAR. DEL #8 Y 4 DEL #5, DOS ESTRIBOS DEL #3 @ 20 CM., ACA BADO APARENTE. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.PREMEZ.F-C=250 | Concreto Premezclado F'c=250 Kg/cm2 T.M.A. 3/4" revenimiento tiro directo | M3 | 0.672000 | $965.00 | $648.48 |
| BOMBEO | SERVICIO DE BOMBEO | M3 | 0.672000 | $125.00 | $84.00 |
| CIMBRAPLAY 16 MM | CIMBRAPLAY 16MM | M2 | 0.800000 | $95.00 | $76.00 |
| CLAVO DE 2 1/2" A 3 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.400000 | $13.00 | $5.20 |
| CHAFLAN 1" | CHAFLAN 1" | Ml | 4.000000 | $3.20 | $12.80 |
| MADERA DE PINO DE 3A | MADERA DE PINO DE 3a. | PT | 3.200000 | $7.50 | $24.00 |
| DESMOLDANTE | DESMOLDANTE | LT | 1.000000 | $13.80 | $13.80 |
| ACERO ALAM | ALAMBRON DE 1/4" | KG | 1.500000 | $10.00 | $15.00 |
| ACE#5 | ACERO DE REFUERZO DE 5/8" #5 | KG | 27.500000 | $8.20 | $225.50 |
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 19.200000 | $8.50 | $163.20 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.000000 | $12.00 | $0.00 |
| Suma de Material | $1,267.98 | ||||
| Mano de Obra | |||||
| CUAD OC 62 | (1 Of. Fierrero + 1 Ayud.) | jor | 0.250000 | $763.77 | $190.94 |
| CUAD OC 11 | (1 Of. Carpintero O.N. + 1 Ayud.) | jor | 0.400000 | $763.77 | $305.51 |
| CUAD OC 05 | (1 Of. Albañil + 5 Peones) | jor | 0.080000 | $2,048.30 | $163.86 |
| Suma de Mano de Obra | $660.31 | ||||
| Equipo | |||||
| VIBRADORCONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.900000 | $21.44 | $19.30 |
| Suma de Equipo | $19.30 | ||||
| Auxiliar | |||||
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Auxiliar | $0.00 | ||||
| Costo Directo | $1,947.59 |