| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| B-8 | FABRICACION DE ESCALONES DE CONCRETO | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 200 | CONCRETO PREMEZCLADO DE F?C=200 KG/CM2 | M3 | 0.026400 | $910.00 | $24.02 |
| MADERA DE PINO DE 3A | MADERA DE PINO DE 3a. | PT | 1.800000 | $7.50 | $13.50 |
| MALLA 6/6 10-10 | MALLA ELECTROSOLDADA 6/6 10-10 | M2 | 0.510000 | $11.00 | $5.61 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.100000 | $12.00 | $1.20 |
| CLAVO DE 2 1/2" A 3 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.100000 | $13.00 | $1.30 |
| Suma de Material | $45.63 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | (1 Of. Albañil + 1 Peon) | jor | 0.100000 | $763.77 | $76.38 |
| Suma de Mano de Obra | $76.38 | ||||
| Costo Directo | $122.01 |