| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| E-3 | LOSA NERVADA EN AZOTEA DE MEZANINE, INCLUYE: CIMBRA, ACERO DE REF., MALLA ELECTROSOLDADA 6X6-6/6, CONCRETO F'C=250 KG/CM2, RENTA DE CASETONES, DESCIMBRADO Y LIMPIEZA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.PREMEZ.F-C=250 | Concreto Premezclado F'c=250 Kg/cm2 T.M.A. 3/4" revenimiento tiro directo | M3 | 0.200000 | $965.00 | $193.00 |
| CASETON 63.5X63.5 | CASETON FIBRA DE VIDRIO 63.5X63.5 CM | PZA | 1.600000 | $47.00 | $75.20 |
| BOMBEO | SERVICIO DE BOMBEO | M3 | 0.200000 | $125.00 | $25.00 |
| CIMBRAPLAY 16 MM | CIMBRAPLAY 16MM | M2 | 0.200000 | $95.00 | $19.00 |
| CLAVO DE 2 1/2" A 3 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.200000 | $13.00 | $2.60 |
| CHAFLAN 1" | CHAFLAN 1" | Ml | 1.000000 | $3.20 | $3.20 |
| MADERA DE PINO DE 3A | MADERA DE PINO DE 3a. | PT | 3.200000 | $7.50 | $24.00 |
| DESMOLDANTE | DESMOLDANTE | LT | 1.000000 | $13.80 | $13.80 |
| ACE#5 | ACERO DE REFUERZO DE 5/8" #5 | KG | 22.000000 | $8.20 | $180.40 |
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 11.000000 | $8.50 | $93.50 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 1.260000 | $12.00 | $15.12 |
| Suma de Material | $644.82 | ||||
| Mano de Obra | |||||
| CUAD OC 62 | (1 Of. Fierrero + 1 Ayud.) | jor | 0.170000 | $763.77 | $129.84 |
| CUAD OC 11 | (1 Of. Carpintero O.N. + 1 Ayud.) | jor | 0.100000 | $763.77 | $76.38 |
| CUAD OC 05 | (1 Of. Albañil + 5 Peones) | jor | 0.060000 | $2,048.30 | $122.90 |
| Suma de Mano de Obra | $329.12 | ||||
| Equipo | |||||
| VIBRADORCONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.500000 | $21.44 | $10.72 |
| Suma de Equipo | $10.72 | ||||
| Auxiliar | |||||
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.010000 | $0.00 | $0.00 |
| Suma de Auxiliar | $0.00 | ||||
| Costo Directo | $984.66 |