| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| B-4 | FIRME DE CONCRETO DE 10 CM. DE ESPESOR REF. CON MALLA 6X6-10/10. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.PREMEZ.F-C=250 | Concreto Premezclado F'c=250 Kg/cm2 T.M.A. 3/4" revenimiento tiro directo | M3 | 0.132000 | $965.00 | $127.38 |
| MALLA 6/6 10-10 | MALLA ELECTROSOLDADA 6/6 10-10 | M2 | 1.100000 | $11.00 | $12.10 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.010000 | $12.00 | $0.12 |
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 0.200000 | $8.50 | $1.70 |
| CIMBRA METALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.014300 | $80.10 | $1.15 |
| AGUA | AGUA | m3 | 0.021000 | $42.75 | $0.90 |
| PEINE METALICO | PEINE METALICO PARA ACABADO DE CONCRETO | PZA | 0.000500 | $857.58 | $0.43 |
| Suma de Material | $143.77 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | (1 Of. Albañil + 5 Peones) | jor | 0.025000 | $2,048.30 | $51.21 |
| CUAD OC 62 | (1 Of. Fierrero + 1 Ayud.) | jor | 0.006000 | $763.77 | $4.58 |
| Suma de Mano de Obra | $55.79 | ||||
| Equipo | |||||
| REGLA VIBRATORIA | REGLA VIBRATORIA | hora | 0.003571 | $212.29 | $0.76 |
| ALLANADORA MECANIC. | ALLANADORA MECANICA CON ASPAS | hora | 0.016665 | $167.59 | $2.79 |
| Suma de Equipo | $3.55 | ||||
| Costo Directo | $203.11 |