| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| G-10 | FORJADO DE PRETIL DE CONCRETO CON TAPA EN REGISTRO DE ENTRADA A CISTERNA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 200 | CONCRETO PREMEZCLADO DE F?C=200 KG/CM2 | M3 | 0.300000 | $910.00 | $273.00 |
| ANGULO DIF. MEDIDAS | ANGULO METALICO | KG | 18.000000 | $10.00 | $180.00 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 2.000000 | $30.00 | $60.00 |
| LAMINA CAL. 16 | LAMINA CAL. 16 | KG | 40.000000 | $28.00 | $1,120.00 |
| MADERA DE PINO DE 3A | MADERA DE PINO DE 3a. | PT | 3.600000 | $7.50 | $27.00 |
| CIMBRAPLAY 16 MM | CIMBRAPLAY 16MM | M2 | 0.400000 | $95.00 | $38.00 |
| MALLA 6/6 6-6 | MALLA ELECTROSOLDADA 6X6/ 6-6 | M2 | 1.100000 | $18.43 | $20.27 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.100000 | $12.00 | $1.20 |
| CLAVO DE 2 1/2" A 3 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.100000 | $13.00 | $1.30 |
| Suma de Material | $1,720.77 | ||||
| Mano de Obra | |||||
| CUAD OC PAIL | (1 Of. Pailero + 1 Ayud.) | jor | 0.400000 | $783.30 | $313.32 |
| CUAD OC 09 | (1 Of. Albañil + 1 Peon) | jor | 0.100000 | $763.77 | $76.38 |
| CUAD OC 62 | (1 Of. Fierrero + 1 Ayud.) | jor | 0.020000 | $763.77 | $15.28 |
| CUAD OC 11 | (1 Of. Carpintero O.N. + 1 Ayud.) | jor | 0.120000 | $763.77 | $91.65 |
| Suma de Mano de Obra | $496.62 | ||||
| Costo Directo | $2,217.40 |