| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 047G11A09. | De f'c = 250 kg/cm² en parapetos y guarniciones | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-05 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2, ELABORADO CON CEMENTO RESISTENTE A LOS SULFATOS Y ALCALISIS | M3 | 1.050000 | $1,125.00 | $1,181.25 |
| AGUA EN PIPA | AGUA PUESTA EN OBRA ACARREADA EN PIPA. | M3 | 0.521700 | $50.00 | $26.09 |
| PAVIMENTO-06 | MEMBRANA DE CURADO | LT | 1.730000 | $8.89 | $15.38 |
| CIMBRA-04 | MADERA DE PINO | PT | 4.780000 | $7.50 | $35.85 |
| CIMBRA-003 | CLAVO DE 2 1/2" A 4 1/2" | KG | 0.690000 | $13.04 | $9.00 |
| Suma de Material | $1,267.56 | ||||
| Mano de Obra | |||||
| CUADRILLA CARO. ON | (1 Of. Carpintero O.N. + 1Ayte). | JOR | 0.083333 | $759.03 | $63.25 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.500000 | $568.94 | $284.47 |
| Suma de Mano de Obra | $347.72 | ||||
| Costo Directo | $1,615.28 |