| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| M-08 | CADENA DE CERRAMIENTO CONCRETO F'C=250KG/CM2, SECCION10X25 CM. REF. CON ESTRIBOS DE 1/2" A CADA 25 CM. Y 4 VARILLAS DEL No. 4, INCLUYE: CIMBRADO Y DESCIMBRADO. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.027500 | $949.80 | $26.12 |
| ACERO | ACERO REF.VAR.DIAM. | kg | 8.120000 | $10.55 | $85.67 |
| MADERA-3 | MADERA DE PINO DE 3A. | PT | 3.200000 | $7.49 | $23.97 |
| MADERA-6 | CIMBRAPLAY 16 MM HOJA DE 1.22 X 2.44 | M2 | 0.150000 | $87.54 | $13.13 |
| CLAVO | CLAVO | KG | 0.110000 | $13.08 | $1.44 |
| DESMOLDANTE | DESMOLDANTE SEPAROL MARCA SIKA | litro | 0.400000 | $10.02 | $4.01 |
| Suma de Material | $154.33 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.166667 | $783.37 | $130.56 |
| Suma de Mano de Obra | $130.56 | ||||
| Herramienta | |||||
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $284.89 |