| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| H-1 | SUMINISTRO Y COLOCACION Y ANCLAJE EN PISO, DE MARCO PARA PUERTA, DE 2.20X1.50 M., FORMADO CON PERFIL ZINTRO ZR-200 CAL. 14, INCLUYE: FIJACION EN PISO AHOGANDO EN CONCRETO, CORTE CON DISCO, PARA DELIMITAR EL AREA DE FIRME A DEMOLER, DEMOLICION, LIMPIEZA, APLICACION DE PRIMARIO ANTICORROSIVO. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PERFIL ZINTRO ZR-200 | CAL. 14 | ML | 7.200000 | $36.00 | $259.20 |
| 1.-PINPRIM | Primario para metal | lt | 0.300000 | $42.00 | $12.60 |
| 1.-PINSOLTHI | Thiner normal opex | ltr. | 0.250000 | $24.00 | $6.00 |
| DISCO PARA CORTE | DE PIEDRA | PZA | 0.030000 | $180.00 | $5.40 |
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.010000 | $949.80 | $9.50 |
| ACERO | ACERO REF.VAR.DIAM. | kg | 0.557000 | $10.55 | $5.88 |
| SOLDADURA | SOLDADURA | KG | 0.250000 | $35.00 | $8.75 |
| Suma de Material | $307.32 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.200000 | $783.37 | $156.67 |
| CUADRILLA 19 | Cuadrilla de pintores(1 OF. PINTOR + 1 AYUDANTE) | Jor. | 0.090000 | $948.27 | $85.34 |
| JOGP031 | Cuadrilla de soldadores. Incluye :soldador, ayudante, cabo y herramienta. | Jor | 0.200000 | $638.49 | $127.70 |
| Suma de Mano de Obra | $369.72 | ||||
| Equipo | |||||
| CORTADORA PARA PISO | cortadora de piso | HR | 0.400000 | $24.31 | $9.72 |
| EQASO001 | Soldadora Lincon SAE 300 amp. K1277 mot. Perkins 4236, 4 cil, 60 hp, 1600 r.p.m. (sin operador). | Hr | 0.500000 | $8.07 | $4.04 |
| Suma de Equipo | $13.76 | ||||
| Costo Directo | $690.80 |