| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1.36A | APLANADO FINO EN MUROS EXTERIORES DE HASTA 6 MTS. DE ALTURA CON MORTERO CEMENTO ARENA 1:4, INCLUYE: MATERIALES, MANO DE OBRA, HERRAMIENTA, Y ANDAMIOS. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | ACARREO INTERNO | M3 | 0.040000 | $40.00 | $1.60 |
| Suma de Material | $1.60 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.150000 | $644.92 | $96.74 |
| Suma de Mano de Obra | $96.74 | ||||
| Herramienta | |||||
| ANDAMIOS | ANDAMIOS | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MORTERO CEM-ARE 1:4 | Mortero cemento arena 1 : 4 | M3 | 0.022000 | $920.21 | $20.24 |
| Suma de Auxiliar | $20.24 | ||||
| Costo Directo | $118.58 |