| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1.09 | PLANTILLA DE CONCRETO DE F'C=100 KG/CM2 DE 5 CMS. DE ESPESOR. INCLUYE: MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.150 KG/CM2 PREM | tiro directo rev.8-11 | m3 | 0.052500 | $850.00 | $44.63 |
| MADERA-2 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.500000 | $7.50 | $3.75 |
| CLAVO (VARIAS MED.) | CLAVO DE ACERO AL CARBON DE 2" A 4" | KG | 0.020000 | $17.00 | $0.34 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.100000 | $14.00 | $1.40 |
| Suma de Material | $50.12 | ||||
| Mano de Obra | |||||
| CUADRILLA NO.06 | (1 OFICIAL ALBAÑIL + 1 PEON) | JOR | 0.040000 | $684.12 | $27.36 |
| Suma de Mano de Obra | $27.36 | ||||
| Costo Directo | $77.48 |