| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 283 | Banquetas de concreto f`c 150 k/c2, de 8 cm. De espesor, el concepto incluye la preparación de terreno, afine cimbra, colado, acabado rallado fino. | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA PARA TERRACERIAS | M3 | 0.005000 | $3.56 | $0.02 |
| AGUA | AGUA PARA TERRACERIAS | M3 | 0.005000 | $3.56 | $0.02 |
| CIM POLIN | Polin 3" x 3 1/2" x 8' regular | pt | 0.550000 | $7.14 | $3.93 |
| CIM POLIN | Polin 3" x 3 1/2" x 8' regular | pt | 0.550000 | $7.14 | $3.93 |
| CONCRETO PRE-03 | CONCRETO PREMEZCLADO F'C=150KG/CM2 | M3 | 0.084000 | $785.00 | $65.94 |
| CONCRETO PRE-03 | CONCRETO PREMEZCLADO F'C=150KG/CM2 | M3 | 0.084000 | $785.00 | $65.94 |
| PAVIMENTO-06 | MEMBRANA DE CURADO WRMEADOWS | LT | 0.150000 | $12.00 | $1.80 |
| PAVIMENTO-06 | MEMBRANA DE CURADO WRMEADOWS | LT | 0.150000 | $12.00 | $1.80 |
| H7BPL005 | Diesel | L | 0.350000 | $5.75 | $2.01 |
| H7BPL005 | Diesel | L | 0.350000 | $5.75 | $2.01 |
| Suma de Material | $147.39 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.071429 | $698.33 | $49.88 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.071429 | $698.33 | $49.88 |
| Suma de Mano de Obra | $99.76 | ||||
| Equipo | |||||
| AMAQUINARIA-92 | PLACA VIBRATORIA CIPSA | HR | 0.025000 | $59.68 | $1.49 |
| AMAQUINARIA-92 | PLACA VIBRATORIA CIPSA | HR | 0.025000 | $59.68 | $1.49 |
| Suma de Equipo | $2.98 | ||||
| Auxiliar | |||||
| SUMINISTRO DE AGUA | suministro de agua en pipa | m3 | 0.035000 | $29.74 | $1.04 |
| SUMINISTRO DE AGUA | suministro de agua en pipa | m3 | 0.035000 | $29.74 | $1.04 |
| Suma de Auxiliar | $2.08 | ||||
| Costo Directo | $252.22 |