| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OXXO-EST-03-10-01 | LOSA ALIGERADA 20CM ESPESOR, A BASE DE SISTEMA VIGUETA Y BOVEDILLA CON CONCRETO F'C=250KG/CM2, VIGUETA PRETENSADA CON FY=6000KG/CM2 Y BOVEDILLA DE POLIESTIRENO DE 0.20X0.61X1.22MTS, MALLA ELECTROSOLDADA 6-6/10-10 CON FY=5000 KG/CM2, INCLUYE: MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO, HABILITADO DE ACERO, VIBRADO, CURADO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. (SEGUN CALCULO ESTRUCTURAL) | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| OC-01-AGRE-04 | Agua | m3 | 0.025000 | $15.00 | $0.38 |
| OC-01-ALIG-01 | Bovedilla 75m/ejes 15x20x68cm | mill | 0.011300 | $9,690.00 | $109.50 |
| OC-01-ALIG-02 | Viga con armadura de 18 s/varilla claro 2.0 m | m | 1.400000 | $40.04 | $56.06 |
| OC-01-MADE-13 | Duela 1" x4"x8 1/4 | pt | 0.041000 | $14.18 | $0.58 |
| OC-01-MADE-06 | Polin 3 1/2 x3 1/2 x8 1/4 | pt | 0.340000 | $7.85 | $2.67 |
| OC-01-MADE-03 | Barrote 1 1/2"x4"x8 1/4 | pt | 0.041000 | $13.83 | $0.57 |
| OC-01-ALBA-06 | Clavo con cabeza de 2" a 4" | kg | 0.016000 | $14.00 | $0.22 |
| Suma de Material | $169.97 | ||||
| Mano de Obra | |||||
| OC-02-CUA-04 | Cuadrilla de albañiles. Incluye : albañil, 2 ayudantes, cabo y herramienta. | Jor | 0.016266 | $1,431.02 | $23.28 |
| Suma de Mano de Obra | $23.28 | ||||
| Auxiliar | |||||
| OC-04-CONP-02 | Concreto premezclado, con botes y carretilla, en columnas, castillos, trabes, vigas, rampas fc=250 kg/cm2, resistencia normal, tamano maximo de agregado 20mm.(3/4"), rev. 18 cm., incluye: bombeo, vibrado, curado, acarreo | m3 | 0.057000 | $1,674.97 | $95.47 |
| OC-04-ACER-06 | Malla electrosoldada 6x6-10/0 en firmes y losas. Incluye : materiales, mano de obra y herramienta. | m2 | 1.100000 | $26.07 | $28.68 |
| Suma de Auxiliar | $124.15 | ||||
| Costo Directo | $317.40 |