| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| HERR-22 | SUMINISTRO, HABILITADO Y MONTAJE DE ESCALERA DE 6.20 M. DE ALTURA PARA SUBIR A TECHUMBRE DE AZOTEA A BASE DE TUBO DE 2" Y TUBO DE 1-1/2" COMO PELDA脩OS INCLUYE : PLACAS DE ANCLAJE DE 3" DE DI脕METRO Y 1/4" DE ESPESOR CON TAQUETE DE 1/2", UNA MANO DE PRIMARIO ANTICORROSIVO Y ACABADO ESMALTE EN COLOR BLANCO, LIMPIEZA SOLDADURA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCI脫N. | PZA |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-TUBO 2 1/2" | TUBO 2 1/2" CED. 40 | KG | 89.508496 | $18.17 | $1,626.37 |
| CHE-MOTO-TUBO | TUBO DE 1" de diametro CED. 40 | kg | 36.816560 | $18.16 | $668.59 |
| CH-TAQUETES HILT-3/8 | TAQUETES HILTI DE 3/8 | PZA | 2.000000 | $20.00 | $40.00 |
| CHE-ESTRUC-16 | PLACA DE ACERO A-36 DE 3/16" | kg | 0.500000 | $13.59 | $6.80 |
| CHE-COMBUST-06 | GAS MARCA VERAGAS | KG | 8.000000 | $8.70 | $69.60 |
| CHE-COMBUST-05 | OXIGENO | M3 | 3.000000 | $52.00 | $156.00 |
| CHE-ESTRUC-01 | SOLDADURA E-7018 DE 1/8" | KG | 5.000000 | $52.00 | $260.00 |
| CHE-DISCO ABRASIVO | DISCO ABRASIVO | PZA | 2.500000 | $45.00 | $112.50 |
| CHE-FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.100000 | $0.00 | $0.00 |
| Suma de Material | $2,939.85 | ||||
| Mano de Obra | |||||
| CUA-CHE-12 | OFICIAL SOLDADOR, OFICIAL TUBERO, AYUDANTE, PEON | JOR | 3.000000 | $1,837.89 | $5,513.67 |
| Suma de Mano de Obra | $5,513.67 | ||||
| Equipo | |||||
| CHE-EQUIPO-027 | Equipo de corte de oxi-butano | HR | 3.000000 | $8.47 | $25.41 |
| CHE-EQUIPO-007 | PULIDORA BLACK AND DECKER 4000 R.P.M. | HR | 5.000000 | $20.64 | $103.20 |
| CHE-EQUIPO-002 | SOLDADORA LINCOLN SAE 300 AMP. K 1277 MOT. PERKINS 4236, 4 CIL. 60 HP. 1600 R.P.M. | HR | 6.000000 | $8.70 | $52.20 |
| Suma de Equipo | $180.81 | ||||
| Auxiliar | |||||
| PRIMARIO ANTICORR | PRIMARIO ANTICORROSIVO | M2 | 3.500000 | $46.53 | $162.86 |
| PINTUR-ESMALTE | APLICACION DE PINTURA DE ESMALTE COMEX 100.00 | M2 | 3.500000 | $109.71 | $383.99 |
| Suma de Auxiliar | $546.84 | ||||
| Costo Directo | $9,181.17 |