| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALBAÑI-03 | DALA DE CERRAMIENTO SECCION 0.15 X 0.20 MT., CONCRETO F'C=200 KG/CM2, AGREGADO MAXIMO 3/4", CIMBRA 2 CARAS, REFORZADA CON 4 VARILLAS DE 3/8", ESTRIBOS DE 1/4" A/C 20 CM., INCLUYE: MATERIAL, MANO DE OBRA, DESPERDICIOS Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-CIMBRA-01 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 2.133300 | $9.85 | $21.01 |
| CHE-CIMBRA-01 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 2.133300 | $9.85 | $21.01 |
| CHE-CIMBRA-07 | CIMBRAPLAY DE PINO DE 16 MM 1 CARA | HOJA | 0.080000 | $315.00 | $25.20 |
| CHE-CIMBRA-07 | CIMBRAPLAY DE PINO DE 16 MM 1 CARA | HOJA | 0.080000 | $315.00 | $25.20 |
| CHE-ACERO-REFUER-02 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | TON | 0.002339 | $8,965.51 | $20.97 |
| CHE-ACERO-REFUER-02 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | TON | 0.002339 | $8,965.51 | $20.97 |
| CHE-ACERO-REFUER-05 | ALAMBRON LISO DE 1/4" ( NO. 2 ) | TON | 0.000843 | $12,000.00 | $10.12 |
| CHE-ACERO-REFUER-05 | ALAMBRON LISO DE 1/4" ( NO. 2 ) | TON | 0.000843 | $12,000.00 | $10.12 |
| CHE-ACERO-REFUER-06 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $14.00 | $2.80 |
| CHE-ACERO-REFUER-06 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $14.00 | $2.80 |
| CHE-CIMBRA-02 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.135000 | $13.75 | $1.86 |
| CHE-CIMBRA-02 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.135000 | $13.75 | $1.86 |
| CHE-COMBUST-01 | COMBUSTIBLE DIESEL | LT | 0.240000 | $8.50 | $2.04 |
| CHE-COMBUST-01 | COMBUSTIBLE DIESEL | LT | 0.240000 | $8.50 | $2.04 |
| Suma de Material | $167.99 | ||||
| Mano de Obra | |||||
| CUA-CHE-03 | CUADRILLA ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.250000 | $997.67 | $249.42 |
| CUA-CHE-03 | CUADRILLA ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.250000 | $997.67 | $249.42 |
| Suma de Mano de Obra | $498.84 | ||||
| Auxiliar | |||||
| CHE-CONCRETO200 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.031500 | $1,091.27 | $34.38 |
| CHE-CONCRETO200 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.031500 | $1,091.27 | $34.38 |
| Suma de Auxiliar | $68.75 | ||||
| Costo Directo | $735.58 |