| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIST-11 | SUMINISTRO, HABILITADO Y MONTAJE DE ESCALERA PARA CISTERNA BASE DE PERFIL PTR 2" x 2" Y TUBO DE 1" INCLUYE : PLACAS DE ANCLAJE DE 4" x 4" Y 1/4" DE ESPESOR CON TAQUETE DE 1/2", DOS MANOS DE PRIMARIO ANTICORROSIVO, LIMPIEZA, SOLDADURA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-ESTRUC-151 | ptr de 2 1/2" x 2 1/2" rojo | kg | 31.870000 | $12.11 | $385.95 |
| SOLERA DE 1/4" X 4" | solera de 1/4" x 4" | kg | 1.500000 | $14.25 | $21.38 |
| MOTO-TUBO | TUBO DE 1" de diametro CED. 40 | kg | 29.500000 | $18.16 | $535.72 |
| TAQUETE TMP | taquete tmp de 1/2" x 41/2" expansivo | pza | 6.000000 | $25.30 | $151.80 |
| CHE-COMBUST-06 | GAS MARCA VERAGAS | KG | 6.000000 | $8.70 | $52.20 |
| CHE-COMBUST-05 | OXIGENO | M3 | 2.000000 | $52.00 | $104.00 |
| CHE-ESTRUC-01 | SOLDADURA E-7018 DE 1/8" | KG | 4.000000 | $52.00 | $208.00 |
| DISCO PARA DESBASTE | disco para desbaste | pza | 2.000000 | $20.50 | $41.00 |
| Suma de Material | $1,500.04 | ||||
| Mano de Obra | |||||
| CUA-CHE-11 | CUADRILLA DE SOLDADORES | JOR | 2.500000 | $1,530.65 | $3,826.63 |
| Suma de Mano de Obra | $3,826.63 | ||||
| Equipo | |||||
| CHE-EQUIPO-027 | Equipo de corte de oxi-butano | HR | 2.000000 | $8.47 | $16.94 |
| CHE-EQUIPO-034 | Esmeriladora | HR | 4.000000 | $2.88 | $11.52 |
| CHE-EQUIPO-002 | SOLDADORA LINCOLN SAE 300 AMP. K 1277 MOT. PERKINS 4236, 4 CIL. 60 HP. 1600 R.P.M. | HR | 6.000000 | $8.70 | $52.20 |
| Suma de Equipo | $80.66 | ||||
| Auxiliar | |||||
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.100000 | $0.00 | $0.00 |
| PRIMARIO ANTICORR | PRIMARIO ANTICORROSIVO | M2 | 3.000000 | $46.53 | $139.59 |
| PINTUR-ESMALTE | APLICACION DE PINTURA DE ESMALTE COMEX 100.00 | M2 | 3.000000 | $109.71 | $329.13 |
| Suma de Auxiliar | $468.72 | ||||
| Costo Directo | $5,876.05 |