| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALBAÑI-02 | CASTILLO DE CONCRETO AHOGADO C-3 ( EN 1 HUECO ) CONC. F'C=150 KG/CM2-3/4" REF. CON 1 VARILLA R.N. DE 3/8" ESTRIBOS DE 1/4" A/C 2 HILADAS, INCLUYE: MATERIAL, MANO DE OBRA, HERRAMIENTA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCCION. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-ACERO-REFUER-02 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | TON | 0.000584 | $8,965.51 | $5.24 |
| CHE-ACERO-REFUER-02 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | TON | 0.000584 | $8,965.51 | $5.24 |
| CHE-ANDAMIO-01 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.019200 | $18.71 | $0.36 |
| CHE-ANDAMIO-01 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.019200 | $18.71 | $0.36 |
| Suma de Material | $11.19 | ||||
| Mano de Obra | |||||
| CUA-CHE-03 | CUADRILLA ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.060000 | $997.67 | $59.86 |
| CUA-CHE-03 | CUADRILLA ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.060000 | $997.67 | $59.86 |
| Suma de Mano de Obra | $119.72 | ||||
| Auxiliar | |||||
| CHE-CONCRETO150 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 1 1/2" | M3 | 0.010500 | $1,026.23 | $10.78 |
| CHE-CONCRETO150 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 1 1/2" | M3 | 0.010500 | $1,026.23 | $10.78 |
| Suma de Auxiliar | $21.55 | ||||
| Costo Directo | $152.46 |