| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HERR-23 | SUMINISTRO, HABILITADO Y MONTAJE DE BARANDAL A BASE DE TUBO DE 2-1/2" CED. 40 INCLUYE :CODOS, PLACAS DE ANCLAJE DE 4" x 4" Y 1/4" DE ESPESOR CON TAQUETE DE 1/4", DOS MANOS DE PRIMARIO ANTICORROSIVO, LIMPIEZA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN. | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-TUBO 2 1/2" | TUBO 2 1/2" CED. 40 | KG | 21.700000 | $18.17 | $394.29 |
| CHE-TUBO 2 1/2" | TUBO 2 1/2" CED. 40 | KG | 21.700000 | $18.17 | $394.29 |
| CHE-ESTRUC-16 | PLACA DE ACERO A-36 DE 3/16" | kg | 1.680000 | $13.59 | $22.83 |
| CHE-ESTRUC-16 | PLACA DE ACERO A-36 DE 3/16" | kg | 1.680000 | $13.59 | $22.83 |
| CH-TAQUETES HILT-3/8 | TAQUETES HILTI DE 3/8 | PZA | 1.000000 | $20.00 | $20.00 |
| CH-TAQUETES HILT-3/8 | TAQUETES HILTI DE 3/8 | PZA | 1.000000 | $20.00 | $20.00 |
| CHE-COMBUST-06 | GAS MARCA VERAGAS | KG | 0.300000 | $8.70 | $2.61 |
| CHE-COMBUST-06 | GAS MARCA VERAGAS | KG | 0.300000 | $8.70 | $2.61 |
| CHE-COMBUST-05 | OXIGENO | M3 | 0.500000 | $52.00 | $26.00 |
| CHE-COMBUST-05 | OXIGENO | M3 | 0.500000 | $52.00 | $26.00 |
| CHE-ESTRUC-01 | SOLDADURA E-7018 DE 1/8" | KG | 0.600000 | $52.00 | $31.20 |
| CHE-ESTRUC-01 | SOLDADURA E-7018 DE 1/8" | KG | 0.600000 | $52.00 | $31.20 |
| CHE-DISCO ABRASIVO | DISCO ABRASIVO | PZA | 0.600000 | $45.00 | $27.00 |
| CHE-DISCO ABRASIVO | DISCO ABRASIVO | PZA | 0.600000 | $45.00 | $27.00 |
| CHE-FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.007849 | $0.00 | $0.00 |
| CHE-FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.007849 | $0.00 | $0.00 |
| Suma de Material | $1,047.86 | ||||
| Mano de Obra | |||||
| CUA-CHE-12 | OFICIAL SOLDADOR, OFICIAL TUBERO, AYUDANTE, PEON | JOR | 0.700000 | $1,837.89 | $1,286.52 |
| CUA-CHE-12 | OFICIAL SOLDADOR, OFICIAL TUBERO, AYUDANTE, PEON | JOR | 0.700000 | $1,837.89 | $1,286.52 |
| Suma de Mano de Obra | $2,573.05 | ||||
| Equipo | |||||
| CHE-EQUIPO-027 | Equipo de corte de oxi-butano | HR | 1.000000 | $8.47 | $8.47 |
| CHE-EQUIPO-027 | Equipo de corte de oxi-butano | HR | 1.000000 | $8.47 | $8.47 |
| CHE-EQUIPO-007 | PULIDORA BLACK AND DECKER 4000 R.P.M. | HR | 1.000000 | $20.64 | $20.64 |
| CHE-EQUIPO-007 | PULIDORA BLACK AND DECKER 4000 R.P.M. | HR | 1.000000 | $20.64 | $20.64 |
| CHE-EQUIPO-002 | SOLDADORA LINCOLN SAE 300 AMP. K 1277 MOT. PERKINS 4236, 4 CIL. 60 HP. 1600 R.P.M. | HR | 1.000000 | $8.70 | $8.70 |
| CHE-EQUIPO-002 | SOLDADORA LINCOLN SAE 300 AMP. K 1277 MOT. PERKINS 4236, 4 CIL. 60 HP. 1600 R.P.M. | HR | 1.000000 | $8.70 | $8.70 |
| Suma de Equipo | $75.62 | ||||
| Auxiliar | |||||
| PINTUR-ESMALTE | APLICACION DE PINTURA DE ESMALTE COMEX 100.00 | M2 | 0.500000 | $109.71 | $54.86 |
| PINTUR-ESMALTE | APLICACION DE PINTURA DE ESMALTE COMEX 100.00 | M2 | 0.500000 | $109.71 | $54.86 |
| PRIMARIO ANTICORR | PRIMARIO ANTICORROSIVO | M2 | 0.750000 | $46.53 | $34.90 |
| PRIMARIO ANTICORR | PRIMARIO ANTICORROSIVO | M2 | 0.750000 | $46.53 | $34.90 |
| Suma de Auxiliar | $179.51 | ||||
| Costo Directo | $3,876.03 |