| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP0 | SUMINISTRO, HABILITADO Y COLOCACIÓN DE MURO Y PLAFONES (M-5) COMPLEMENTARIOS FIJOS HASTA UNA ALTURA MÁXIMA DE 2.50 m. A BASE DE MALLA CRIBA GALVANIZADA DE 1" Y PERFILES ZINTRO EN BASTIDOR PARA MALLA INCLUYE : ELEMENTOS DE SUJECCIÓN, SOLDADURA, EQUIPO, HERRAMIENTA, FLETES, UNA MANO DE PRIMARIO ANTICORROSIVO, ACABADO CON PINTURA DE ESMALTE SATINADA EN COLOR BLANCO COMEX 100, LIMPIEZA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-PERFIL ZINTRO-02 | PERFIL ZINTRO ZP-030 | KG | 1.716000 | $18.10 | $31.06 |
| CHE-PERFIL ZINTRO-08 | PERFIL TUBULAR ZINTRO ZP-400 C-20 | KG | 3.762000 | $18.26 | $68.69 |
| CHE-MALLA TEJIDA-01 | MALLA TEJIDA GALVANIZADA DE 1*1 | M2 | 1.100000 | $340.76 | $374.84 |
| CHE-ESTRUC-01 | SOLDADURA E-7018 DE 1/8" | KG | 0.450000 | $52.00 | $23.40 |
| CHE-BROCA HSS 1/2" | BROCA HSS COBALTO 1/2" | PZA | 0.100000 | $17.64 | $1.76 |
| CHE-DISCO ABRASIVO | DISCO ABRASIVO | PZA | 0.050000 | $45.00 | $2.25 |
| CHE-TAQUETE DE 1/2" | TAQUETE TMP DE 1/2" x 3-3/4" | PZA | 0.150000 | $17.50 | $2.63 |
| Suma de Material | $504.63 | ||||
| Mano de Obra | |||||
| CUA-CHE-26 | CUADRILLA ( 1 PAILERO + 1 AYUDANTE ) | JOR | 0.125000 | $1,022.18 | $127.77 |
| CUA-CHE-13 | CUADRILLA ( MANIOBRAS Y MONTAJE ) | JOR | 0.041667 | $2,470.26 | $102.93 |
| CUA-CHE-12 | OFICIAL SOLDADOR, OFICIAL TUBERO, AYUDANTE, PEON | JOR | 0.083333 | $1,837.89 | $153.16 |
| Suma de Mano de Obra | $383.86 | ||||
| Equipo | |||||
| CHE-EQUIPO-007 | PULIDORA BLACK AND DECKER 4000 R.P.M. | HR | 0.200000 | $20.64 | $4.13 |
| CHE-EQUIPO-002 | SOLDADORA LINCOLN SAE 300 AMP. K 1277 MOT. PERKINS 4236, 4 CIL. 60 HP. 1600 R.P.M. | HR | 0.080500 | $8.70 | $0.70 |
| Suma de Equipo | $4.83 | ||||
| Auxiliar | |||||
| PRIMARIO ANTICORR | PRIMARIO ANTICORROSIVO | M2 | 2.000000 | $46.53 | $93.06 |
| PINTUR-ESMALTE | APLICACION DE PINTURA DE ESMALTE COMEX 100.00 | M2 | 2.000000 | $109.71 | $219.42 |
| Suma de Auxiliar | $312.48 | ||||
| Costo Directo | $1,205.79 |