| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| COL002 | COLUMNA DE SECCION CUADRADA 50 X 50 0 40 X 60 CONCRETO PREMEZCLADO F'C= 250 KG/CM2 A.M. 3/4" ARMADO CON ACERO DE REFUERZO DEL No. 6 10 PZAS Y EST. DEL No. 3 @15 CM , DOBLE ESTRIBO, CIMBRA, DESCIMBRA, VACIADO, VIBRADO, CURADO, INCLUYE: MATERIAL, MANO DE OBRA Y TODO PARA SU EJECUCION. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-ACERO-REFUER-06 | ALAMBRE RECOCIDO NO. 18 | KG | 1.550000 | $14.00 | $21.70 |
| CHE-ACERO-REFUER-02 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | TON | 0.008000 | $8,965.51 | $71.72 |
| CHE-ACERO-REFUER-07 | VARILLA FY=4200 KG/CM2 NO. 6 ( 3/4" ) | TON | 0.040000 | $8,965.51 | $358.62 |
| CHE-CONCRETO-01 | CONCRETO PREMEZC.RR F'C=250 KG/CM2 AGREGADO MAXIMO 3/4" (A) | M3 | 0.262500 | $855.00 | $224.44 |
| CHE-CONCRETO-03 | SOBRE PRECIO POR REV. 14-16 CM AGREG. 3/4" APTO PARA BOMB.(A) | M3 | 0.262500 | $65.00 | $17.06 |
| CHE-ANDAMIO-02 | TORRE DE ANDAMIO DE 6 MTS DE ALTURA | R/DIA | 2.000000 | $25.60 | $51.20 |
| Suma de Material | $744.74 | ||||
| Mano de Obra | |||||
| CUA-CHE-05 | CUADRILLA ( 1 FIERRERO + 1 AYUDANTE ) | JOR | 0.265000 | $997.67 | $264.38 |
| CUA-CHE-06 | CUADRILLA ( 1 ALBAÑIL + 5 PEONES ) | JOR | 0.050000 | $2,779.31 | $138.97 |
| Suma de Mano de Obra | $403.35 | ||||
| Equipo | |||||
| CHE-EQUIPO-005 | VIBRADOR DYNAPAC-KOHLER K-91 4 HP, LONGITUD 14 PIES | HR | 0.200000 | $25.75 | $5.15 |
| Suma de Equipo | $5.15 | ||||
| Auxiliar | |||||
| CHE-CIMBRA-MURO | CIMBRA APARENTE EN MURO, INCLUYE: CIMBRADO, DESCIMBRADO, SUMINISTRO, MATERIALES DE CONSUMO, MANO DE OBRA Y TRABAJOS NECESARIOS. | M2 | 2.000000 | $387.33 | $774.66 |
| Suma de Auxiliar | $774.66 | ||||
| Costo Directo | $1,927.90 |