| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PISO-05 | PISO DE 15 CM. DE ESPESOR EN ANDEN CONCRETO PREMEZCLADO RESISTENCIA A LOS SULFATOS F'C= 250 KG/CM2, ARMADO CON ACERO DE REFUERZO FY=4200KG/CM2, EN TABLEROS NO MAYORES DE 4.00 MTS DE ANCHO Y LARGO, VACIADO CON BOMBA, INCLUYE: TRAZO, NIVELACION, EXCAVACION, CIMBRA, DESCIMBRA, VIBRADO A REGLA VIBRADORA, CURADO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. ( BASE DE CONCRETO PARA EQUIPOS EN AREA DE SUBESTACION ) | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-CONCRETO-021 | CONCRETO PREMEZCLADO MR - 38 | M3 | 0.155000 | $994.84 | $154.20 |
| CHE-CIMBRA-01 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 1.050000 | $9.85 | $10.34 |
| CHE-CONCRETO-05 | BOMBEO DE CONCRETO | m3 | 0.155000 | $110.00 | $17.05 |
| CHE-ACERO-REFUER-01 | VARILLA FY=4200 KG/CM2 NO. 4 ( 1/2" ) | TON | 0.015936 | $8,965.51 | $142.87 |
| CHE-ACERO-REFUER-06 | ALAMBRE RECOCIDO NO. 18 | KG | 0.398400 | $14.00 | $5.58 |
| Suma de Material | $330.04 | ||||
| Mano de Obra | |||||
| CUA-CHE-06 | CUADRILLA ( 1 ALBAÑIL + 5 PEONES ) | JOR | 0.050000 | $2,779.31 | $138.97 |
| Suma de Mano de Obra | $138.97 | ||||
| Equipo | |||||
| CHE-EQUIPO-028 | REGLA VIBRATORIA | HR | 0.035000 | $171.53 | $6.00 |
| Suma de Equipo | $6.00 | ||||
| Auxiliar | |||||
| CHE-CIMBRA-PISO | CIMBRA EN PISOS DE CONCRETO DE 15 CMS DE ESPESOR INCLUYE CHAFLAN Y PERFORACIONES A CADA 60 CMS PARA PASAJUNTAS | M2 | 1.000000 | $35.35 | $35.35 |
| Suma de Auxiliar | $35.35 | ||||
| Costo Directo | $510.36 |