| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| COL001 | COLUMNA DE CONCRETO DE SECCION CIRCULAR DE 60 CMS DE DIAMETRO , ARMADO CON ACERO DEL No. 8 / 12 VARS. Y EST. DEL No. 3@ 15 CM , CONCRETO PREMEZCLADO F'C= 300 KG/CM2 A.M. 3/4, CIMBRA Y DESCIMBRA , SONOTUBO DE 60 CM, INCLUYE: MATERIAL, MANO DE OBRA Y TODO PARA SU CORRECTA EJECUCION. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-ACERO-REFUER-06 | ALAMBRE RECOCIDO NO. 18 | KG | 1.650000 | $14.00 | $23.10 |
| CHE-ACERO-REFUER-02 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | TON | 0.011000 | $8,965.51 | $98.62 |
| CHE-ACERO-REFUER-03 | VARILLA FY=4200 KG/CM2 NO. 8 ( 1" ) | TON | 0.055000 | $8,965.51 | $493.10 |
| CHE-CONCRETO-02 | CONCRETO PREMEZCLADO DE 300 KG/CM2 CON AGREGADO 3/4" REV. 10-12 | M3 | 0.300000 | $1,114.56 | $334.37 |
| CHE-CONCRETO-03 | SOBRE PRECIO POR REV. 14-16 CM AGREG. 3/4" APTO PARA BOMB.(A) | M3 | 0.300000 | $65.00 | $19.50 |
| ZSONOTUBO 50CM | SONOTUBO DE 60 CM | ML | 1.050000 | $210.80 | $221.34 |
| CHE-ANDAMIO-02 | TORRE DE ANDAMIO DE 6 MTS DE ALTURA | R/DIA | 2.000000 | $25.60 | $51.20 |
| Suma de Material | $1,241.23 | ||||
| Mano de Obra | |||||
| CUA-CHE-05 | CUADRILLA ( 1 FIERRERO + 1 AYUDANTE ) | JOR | 0.370000 | $997.67 | $369.14 |
| CUA-CHE-06 | CUADRILLA ( 1 ALBAÑIL + 5 PEONES ) | JOR | 0.075000 | $2,779.31 | $208.45 |
| Suma de Mano de Obra | $577.59 | ||||
| Equipo | |||||
| CHE-EQUIPO-005 | VIBRADOR DYNAPAC-KOHLER K-91 4 HP, LONGITUD 14 PIES | HR | 0.200000 | $25.75 | $5.15 |
| Suma de Equipo | $5.15 | ||||
| Auxiliar | |||||
| CHE-CIMBRA-MURO | CIMBRA APARENTE EN MURO, INCLUYE: CIMBRADO, DESCIMBRADO, SUMINISTRO, MATERIALES DE CONSUMO, MANO DE OBRA Y TRABAJOS NECESARIOS. | M2 | 1.880000 | $387.33 | $728.18 |
| Suma de Auxiliar | $728.18 | ||||
| Costo Directo | $2,552.15 |