| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALBAÑI-04 | SUMIISTRO Y COLOCACION DE SARDINEL DE CONCRETO FORRADO CON LOSETA CERAMICA DE 10 X 10 CMS. ASENTADO CON CEMENTO CREST, INCLUYE: MATERIAL, MANO DE OBRA, HERRAMIENTA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-ACERO-REFUER-02 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | TON | 0.003000 | $8,965.51 | $26.90 |
| CHE-PISO-02 | LOSETA DE CERAMICA DE 49 x 49 cms, MOD. BOTTICINO COLOR ORO FIORITO | M2 | 0.333000 | $270.69 | $90.14 |
| CHE-AGLUT-03 | CEMENTO CREST BLANCO | KG | 0.000500 | $3.27 | $0.00 |
| CHE-AGLUT-05 | CEMENTO BLANCO EN SACO | TON | 0.001860 | $3,275.58 | $6.09 |
| CHE-AGLUT-02 | AGUA POTABLE | m3 | 0.008000 | $12.00 | $0.10 |
| Suma de Material | $123.23 | ||||
| Mano de Obra | |||||
| CUA-CHE-03 | CUADRILLA ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.125000 | $997.67 | $124.71 |
| Suma de Mano de Obra | $124.71 | ||||
| Equipo | |||||
| CHE-EQUIPO-003 | CORTADORA DE AZULEJO. | HR | 0.055000 | $0.75 | $0.04 |
| Suma de Equipo | $0.04 | ||||
| Auxiliar | |||||
| CHE-CONCRETO100 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.010500 | $957.91 | $10.06 |
| CHE-CIMBRA-MURO | CIMBRA APARENTE EN MURO, INCLUYE: CIMBRADO, DESCIMBRADO, SUMINISTRO, MATERIALES DE CONSUMO, MANO DE OBRA Y TRABAJOS NECESARIOS. | M2 | 0.200000 | $387.33 | $77.47 |
| Suma de Auxiliar | $87.52 | ||||
| Costo Directo | $335.50 |