| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HERR-61 | BASTIDOR DE PTR DE 2" ANCLADO AL MURO DEL EJE 3 CON DOS ELEMENTOS HORIZONTALES UNO INFERIOR Y OTRO SUPERIOR, NUEVE POSTES, DIECIOCHO ANCLAS APOYADAS A MUROS MEDIANTE PLACAS DE 4" x4" X 1/4" PINTADO CON ESMALTE ANTICORROSIVO DE COLOR BLANCO. INCLUYE: TRAZO, CORTE, SOLDADURA, ANCLAJE, PLACA DE APOYO, ANDAMIAJE, PINTURA Y MANO DE OBRA. | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-MOTO-PTR-01 | PTR DE DIFERENTES MEDIDAS | KG | 6.360000 | $16.00 | $101.76 |
| CHE-ESTRUC-16 | PLACA DE ACERO A-36 DE 3/16" | kg | 0.060000 | $13.59 | $0.82 |
| CHE-COMBUST-06 | GAS MARCA VERAGAS | KG | 0.340000 | $8.70 | $2.96 |
| CHE-COMBUST-05 | OXIGENO | M3 | 0.476000 | $52.00 | $24.75 |
| CHE-ESTRUC-01 | SOLDADURA E-7018 DE 1/8" | KG | 1.000000 | $52.00 | $52.00 |
| CHE-DISCO ABRASIVO | DISCO ABRASIVO | PZA | 0.250000 | $45.00 | $11.25 |
| CHE-FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.006000 | $0.00 | $0.00 |
| CH-TAQUETES HILT-3/8 | TAQUETES HILTI DE 3/8 | PZA | 1.000000 | $20.00 | $20.00 |
| Suma de Material | $213.54 | ||||
| Mano de Obra | |||||
| CUA-CHE-26 | CUADRILLA ( 1 PAILERO + 1 AYUDANTE ) | JOR | 0.125000 | $1,022.18 | $127.77 |
| CUA-CHE-12 | OFICIAL SOLDADOR, OFICIAL TUBERO, AYUDANTE, PEON | JOR | 0.125000 | $1,837.89 | $229.74 |
| Suma de Mano de Obra | $357.51 | ||||
| Auxiliar | |||||
| PRIMARIO ANTICORR | PRIMARIO ANTICORROSIVO | M2 | 0.250000 | $46.53 | $11.63 |
| PINTUR-ESMALTE | APLICACION DE PINTURA DE ESMALTE COMEX 100.00 | M2 | 0.250000 | $109.71 | $27.43 |
| Suma de Auxiliar | $39.06 | ||||
| Costo Directo | $610.10 |