| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALBAÑI-16 | MUEBLE DE RECEPCION EN AREA DE BODEGA DE 3.50 X 0.80 , A BASE DE LOSA DE CONCRETO F'C=250 KG/CM2 DE 1O CM DE ESPESOR, ARMADA CON ACERO DE REFUERZO FY=4200KG/CM2 DEL #3 @ 20 CM EN AMBOS SENTIDOS, SOPORTE DE MURO DE BLOCK , CON ACABADO DE AZULEJO BLANCO DE 20 X 30 STRATTO, PEGADO CON CREST Y JUNTEADO CON ,LECHADA DE CEMENTO BLANCO, INCLUYE: MATERIALES, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECT EJECUCION. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-CIMBRA-06 | CHAFLAN DE MADERA DE PINO DE 3A. DE 1" | Ml | 9.200000 | $4.00 | $36.80 |
| CHE-ACERO-REFUER-02 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | TON | 0.050000 | $8,965.51 | $448.28 |
| CHE-ACERO-REFUER-06 | ALAMBRE RECOCIDO NO. 18 | KG | 2.500000 | $14.00 | $35.00 |
| CHE-AGLUT-02 | AGUA POTABLE | m3 | 0.280000 | $12.00 | $3.36 |
| CHE-AGREGADO-07 | BLOCK DE CONCRETO LIGERO DE 15 X 20 X 40 CM | MIL | 0.250000 | $6,465.51 | $1,616.38 |
| Suma de Material | $2,139.81 | ||||
| Mano de Obra | |||||
| CUA-CHE-05 | CUADRILLA ( 1 FIERRERO + 1 AYUDANTE ) | JOR | 1.000000 | $997.67 | $997.67 |
| CUA-CHE-03 | CUADRILLA ( 1 ALBAÑIL + 1 PEON ) | JOR | 3.000000 | $997.67 | $2,993.01 |
| Suma de Mano de Obra | $3,990.68 | ||||
| Auxiliar | |||||
| CHE-CIMBRA-LOSA | CIMBRA APARENTE EN TRABES Y LOSA POR SUPERFICIE DE CONTACTO, INCLUYE: GOTEROS, CIMBRADO, DESCIMBRADO, ACARREOS, MATERIALES, MANO DE OBRA, DESPERDICIOS, HERRAMIENTA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION | M2 | 3.200000 | $343.44 | $1,099.01 |
| CONCRE250 | CONCRETO F´C=250 KG/CM2 PREMEZCLADO | M3 | 0.350000 | $1,088.33 | $380.92 |
| MEZMOR 1:4 | MEZCLA MORTERO CEM-ARENA 1:4 | M3 | 0.250000 | $1,084.56 | $271.14 |
| Suma de Auxiliar | $1,751.06 | ||||
| Concepto | |||||
| ALBAÑI-02 | CASTILLO DE CONCRETO AHOGADO C-3 ( EN 1 HUECO ) CONC. F'C=150 KG/CM2-3/4" REF. CON 1 VARILLA R.N. DE 3/8" ESTRIBOS DE 1/4" A/C 2 HILADAS, INCLUYE: MATERIAL, MANO DE OBRA, HERRAMIENTA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCCION. | ML | 16.000000 | $76.20 | $1,219.20 |
| Suma de Concepto | $1,219.20 | ||||
| Costo Directo | $9,100.76 |