| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP131 | DE 21 MM. DE DIÁMETRO, PARED GRUESA. | M. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBCGPG19 | TUBO CONDUIT GALV. PARED GRUESA DE 19MM | PZA | 0.336667 | $123.00 | $41.41 |
| CODOCGPG19 | CODO CONDUIT GALV. PARED GRUESA DE 19MM | PZA | 0.400000 | $34.00 | $13.60 |
| CAJAREG19-RACO | CAJA REGISTRO GALVANIZADA DE 19MM CON TORNILLO DE TIERRA , CATALOGO 190 , MARCA RACO | PZA | 0.800000 | $21.20 | $16.96 |
| TAPAGALV19-RACO | TAPA GALVANIZADA PARA CAJA REGISTRO DE 19 MM MCA. RACO | PZA | 0.600000 | $12.00 | $7.20 |
| SOBRETAPAGALV-RACO19 | SOBRETAPA GALVANIZADA PARA CAJA REGISTRO DE 19 MM MCA. RACO | PZA | 0.600000 | $16.00 | $9.60 |
| CONTRA-MONIT-19 | CONTRA Y MONITOR GALVANIZADO DE 19MM | PZA | 0.600000 | $4.00 | $2.40 |
| TAQ-SCI-1/4" | TAQUETE SCI 1/4" | PZA | 2.000000 | $3.50 | $7.00 |
| TORN-G1/4X1" | TORNILLO GALVANIZADO DE 1/4" X 1" | PZA | 2.000000 | $0.70 | $1.40 |
| ALAMBREGUIA14 | ALAMBRE GUIA GALVANIZADO DEL # 14 | KG | 0.028000 | $34.60 | $0.97 |
| Suma de Material | $100.54 | ||||
| Mano de Obra | |||||
| CUADRILLA INST. 02 | Cuadrilla de electricista ( Electricista + ayudante) | Jor | 0.054920 | $1,123.09 | $61.68 |
| Suma de Mano de Obra | $61.68 | ||||
| Equipo | |||||
| TARRAJA 1/2"-2" | Tarraja de 1/2" a 2" | HORA | 0.487800 | $2.46 | $1.20 |
| Suma de Equipo | $1.20 | ||||
| Auxiliar | |||||
| SOPORT C/OMEGA 19 | Soporteria a base de abrazadera omega 19 mm, incluye: taquetes, pijas, herramienta. | pza | 0.400000 | $11.17 | $4.47 |
| SOPORT C/UNICANAL 19 | Soporteria a base de abrazadera unicanal 19 mm, incluye: taquetes, pijas, herramienta. | pza | 0.800000 | $16.42 | $13.14 |
| 03-7022 | Torre de trabajo de 0.00 a 4.00 mts. De altura con ruedas. | r/d | 0.029130 | $34.50 | $1.00 |
| Suma de Auxiliar | $18.61 | ||||
| Costo Directo | $182.03 |