| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| OC04-107-005 - | P-8; DE 10 CM. DE ESPESOR. AGREGADO M脕XIMO DE 19 MM. ACABADO PULIDO, COLOR NATURAL, ARMADO CON MALLA 6-6/6-6. | M2 |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO-BOMBA | Bombeo concr.c/bomba | m3 | 0.105000 | $175.00 | $18.38 |
| MEMBRANA | Membrana de curado | L | 0.250000 | $31.48 | $7.87 |
| REVENEMIETNO | revenimiento | m3 | 0.105000 | $80.00 | $8.40 |
| MALLA6 | Malla electrosoldada 6x6/6-6 hoja, rollo de 100m2 | m2 | 1.050000 | $35.00 | $36.75 |
| ADITIVO | Sika Flex 1-A, cartucho de 0.36kg color negro, marca Sika | pza | 0.166667 | $81.47 | $13.58 |
| NJUNTAPISTOLA | PISTOLA CALAFATEADORA | PZA | 0.001250 | $887.00 | $1.11 |
| CONCRETO 250KG | CONCRETO PREMEZC.RN F'C=250 KG/CM2 AGREGADO MAXIMO 3/4" (A) | m3 | 0.084000 | $1,105.00 | $92.82 |
| Suma de Material | $178.90 | ||||
| Mano de Obra | |||||
| A100105-2025 | Cuadrilla de alba帽iles. Incluye : alba帽il, 3 ayudantes, cabo y herramienta. | Jor | 0.028700 | $1,954.32 | $56.09 |
| Suma de Mano de Obra | $56.09 | ||||
| Equipo | |||||
| C990140-3510 | Vibrador de Concreto mot. gasolina 8 hp Kolher flecha 14 cabezal AA48 de 17/8 (45mm). | HR | 0.200000 | $57.64 | $11.53 |
| Suma de Equipo | $11.53 | ||||
| Auxiliar | |||||
| 00-0050 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | m3 | 0.040000 | $98.71 | $3.95 |
| SEP-CON001 | SEPARADOR DE CONCRETO PARA CALZAR ACERO DE REFUERZO. | pieza | 2.000000 | $2.64 | $5.28 |
| Suma de Auxiliar | $9.23 | ||||
| Costo Directo | $255.75 |