| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OC03-083-005 | CUBIERTA DE MULTYTECHO 2" , CAL.26/26, INCLUYE CUMBRERAS Y REMATES PERIMETRALES) | M2. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAT-TECH-02 | LAMINA MT-100 C.26/26 DE 4" COLOR BCO TIPO MULTYPANEL MARCA TERNIUM | ml | 1.042000 | $600.00 | $625.20 |
| MAT-TECH-03 | PLACAS DE FIJACION | pza | 0.261096 | $3.00 | $0.78 |
| MAT-TECH-04 | PIJAS DE 1/4"x5" | pza | 1.044380 | $1.50 | $1.57 |
| MAT-TECH-05 | SELLADOR | pza | 0.110180 | $50.00 | $5.51 |
| MAT-TECH-06 | PIJAS DE 1/4"x7/8" | pza | 2.100000 | $0.75 | $1.58 |
| MAT-TECH-07 | FLETE MONTERREY-CANCUN | flete | 0.003135 | $18,800.00 | $58.94 |
| Suma de Material | $693.57 | ||||
| Mano de Obra | |||||
| CUA99 | 1 of.montador + 4 ayudante A. | Jor | 0.250000 | $2,607.19 | $651.80 |
| Suma de Mano de Obra | $651.80 | ||||
| Costo Directo | $1,345.37 |