| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 6005 | SUMINSITRO E INSTALACION DE SALIDA HIDRAULICA PARA EQUIPO DE AIRE ACONDICIONADO DESDE UNIDAD EVAPORADORA HASTA DESCARGA EN DRENAJE SANITARIO. INCLUYE: TUBERIAS, CODOS, TEES, SOPORTERIA, EXCAVACIONES , RELLENOS, PASOS EN LOSA Y MUROS, SOPORTES TIPO PERA, MATERIALES, HERRAMIENTAS, MANO DE OBRA Y DEM脕S CARGOS CORRESPONDIENTS P.U.O.T. | PZA |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBPVC-RD26-19 | Tuberia de PVC Hidraulico RD-26 mca. Rexolit de 19 mm de diametro | ml | 8.200000 | $7.20 | $59.04 |
| TUBPVC-RD26-13 | Tuberia de PVC Hidraulico RD-13.5 mca. Rexolit de 13 mm de diametro | ml | 3.200000 | $4.80 | $15.36 |
| CODO PVCHID 90X19 | Codo de pvc hidraulico RD-26 de 90x19 mm | pza | 0.250000 | $1.80 | $0.45 |
| CODO PVCHID 90X13 | Codo de pvc hidraulico RD-26 de 90x13 mm | pza | 0.100000 | $1.50 | $0.15 |
| TEEPVC-RD26-19 | TEE PVC HIDRAULICO DE 3/4" DE DIAMETRO | pza | 0.400000 | $2.30 | $0.92 |
| TEEPVC-RD26-13 | TEE PVC HIDRAULICO DE 1/2" DE DIAMETRO | pza | 0.200000 | $2.00 | $0.40 |
| REDPVC-RD26-19X13 | REDUCCION PVC HIDRAULICO DE 3/4"X1/2" DE DIAMETRO | PZA | 0.300000 | $7.50 | $2.25 |
| AISL TERM 13X19MM | AISLAMIENTO TERMICO TIPO INSULTUBE DE 1/2" ESP. PARA TUBO DE COBRE TIPO M DE 3/4" DE DIAMETRO | ml | 0.150000 | $56.00 | $8.40 |
| TAQUETE SCI 1/4" | Taquete tipo SCI de 1/4'' clevis | pza | 4.000000 | $3.20 | $12.80 |
| VARILLA ROSCADA 1/4" | Varilla roscada de 1/4'' de di谩metro x 3.00 m de longitud | pza | 0.800000 | $22.68 | $18.14 |
| ABRAZ PERA 32 | ABRAZADERA PERA PARA TUBERIA DE 32 MM | PZA | 3.000000 | $2.75 | $8.25 |
| TUERCA HEX. 1/4" | Tuerca hexagonal de 1/4'' de diametro | pza | 4.000000 | $0.15 | $0.60 |
| ARAND-GALV-1/4" | Arandela plana galvanizada de 1/4'' | pza | 4.000000 | $0.30 | $1.20 |
| PEGTANGITROS500 | PEGAMENTO TANGIT ROSADO , BOTE DE 500 ML | pza | 0.080000 | $127.80 | $10.22 |
| LIMPIADOR PARA PVC | Limpiador para tubo de PVC de 500 ml | pza | 0.200000 | $41.85 | $8.37 |
| ESTOPA | Estopa | kg | 0.100000 | $19.00 | $1.90 |
| LIJAESMERILFINA | LIJA DE ESMERIL FINA | PZA | 0.800000 | $17.00 | $13.60 |
| SEGUETAD/STAN | Segueta diente standard | pza | 0.140000 | $6.90 | $0.97 |
| Suma de Material | $163.02 | ||||
| Mano de Obra | |||||
| CUADRILLA INST. 08 | Cuadrilla de electricista ( Electricista + ayudante) | Jor | 0.200000 | $1,023.65 | $204.73 |
| Suma de Mano de Obra | $204.73 | ||||
| Auxiliar | |||||
| 03-7022 | TORRE DE TRABAJO DE 0.00 A 4.00 MTS. DE ALTURA CON RUEDAS | R/D | 0.500000 | $37.80 | $18.90 |
| Suma de Auxiliar | $18.90 | ||||
| Costo Directo | $386.65 |