| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | | | | |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.050000 | $1,026.22 | $51.31 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.050000 | $1,026.22 | $51.31 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.050000 | $1,026.22 | $51.31 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.050000 | $1,026.22 | $51.31 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.050000 | $1,026.22 | $51.31 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.050000 | $1,026.22 | $51.31 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.050000 | $1,026.22 | $51.31 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.050000 | $1,026.22 | $51.31 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.050000 | $1,026.22 | $51.31 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.050000 | $1,026.22 | $51.31 |
| Suma de Mano de Obra | | | | $513.11 |
| Auxiliar | | | | |
| 03-2020 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.060000 | $952.41 | $57.14 |
| 03-2020 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.060000 | $952.41 | $57.14 |
| 03-2020 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.060000 | $952.41 | $57.14 |
| 03-2020 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.060000 | $952.41 | $57.14 |
| 03-2020 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.060000 | $952.41 | $57.14 |
| 03-2020 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.060000 | $952.41 | $57.14 |
| 03-2020 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.060000 | $952.41 | $57.14 |
| 03-2020 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.060000 | $952.41 | $57.14 |
| 03-2020 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.060000 | $952.41 | $57.14 |
| 03-2020 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.060000 | $952.41 | $57.14 |
| Suma de Auxiliar | | | | $571.45 |
| Costo Directo | | | | $1,084.56 |