| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 170 | Excavación en cepas en material tipo II, para alojar tubo conduit. | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $243.15 | $81.05 |
| Suma de Mano de Obra | $1,215.75 | ||||
| Costo Directo | $1,215.75 |