| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OESP-08. | SUMNISTRO Y COLOCACION DE SALIDAS ELECTRICAS PARA ALIMENTACION A TORTILLERIA DESDE DESCONECTADOR YA INSTALADO A EQUIPO, ESTE TRABAJO SE REALIZA EN TIEMPO EXTRA Y CON EL PLAFOND YA TERMINADO Y PINTADO CON EL RIESGO QUE ESTO CONLLEVA, INCLUYE CONEXION DEL EQUIPO AUTORIZADO POR STORE PLANNIING, INCLUYE TUBERIA , CONEXIONES Y CABLEADO , PRUEBAS. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO C.G.P.G. 16MM. | TUBO C.G.P.G. 16MM. | ML | 8.700000 | $14.10 | $122.67 |
| TUBO LQT 13 MM | ML | 1.900000 | $18.00 | $34.20 | |
| CONEC LQT 13 MM | PZA | 2.000000 | $22.00 | $44.00 | |
| CABLE CU.DESN. # 12 | CABLE CU DESNUDO CALIBRE 12 MARCA CONDUMEX | ML | 20.000000 | $1.80 | $36.00 |
| CABLE THW-LS CAL.12. | CABLE THWLS DE CAL. 12 AWG, 600 V MARCA CONDUMEX | ML | 60.000000 | $2.60 | $156.00 |
| TUBO C.G.P.G. 21MM. | TUBO C.G.P.G. 21MM. | ML | 7.500000 | $17.80 | $133.50 |
| Suma de Material | $526.37 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 3.000000 | $775.62 | $2,326.86 |
| Suma de Mano de Obra | $2,326.86 | ||||
| Costo Directo | $2,853.23 |