| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALBANI-01-A | SUMINISTRO Y FABRICACION DE MURO DE BLOCK EN AREA DE CAJA GENERAL INCLUYE RELLENO DE CONCRETO DE LOS ALBEOLOS DEL BLOCK, | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-AGREGADO-07 | BLOCK DE CONCRETO LIGERO DE 15 X 20 X 40 CM | MIL | 0.013000 | $6,465.51 | $84.05 |
| CHE-ACERO-REFUER-01 | VARILLA FY=4200 KG/CM2 NO. 4 ( 1/2" ) | TON | 0.001300 | $10,450.00 | $13.59 |
| CHE-CONCRETO-01 | CONCRETO PREMEZC.RR F'C=250 KG/CM2 AGREGADO MAXIMO 3/4" (A) | M3 | 0.050000 | $985.72 | $49.29 |
| CHE-ACERO-REFUER-08 | REFUERZO HORIZONTAL PARA MURO DE BLOCK ESCALERILLA | Ml | 2.600000 | $8.70 | $22.62 |
| CHE-ANDAMIO-01 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.041600 | $18.71 | $0.78 |
| Suma de Material | $170.32 | ||||
| Mano de Obra | |||||
| CUA-CHE-03 | CUADRILLA ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.350000 | $1,006.54 | $352.29 |
| Suma de Mano de Obra | $352.29 | ||||
| Auxiliar | |||||
| 03-0290 | MORTERO CEMENTO-CALHIDRA-ARENA 1:1:6 | M3 | 0.012000 | $868.16 | $10.42 |
| Suma de Auxiliar | $10.42 | ||||
| Costo Directo | $533.03 |