| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| I.1 | SUMINISTRO, HABILITADO, FABRICACIÓN Y MONTAJE DE ARMADURAS METÁLICAS A BASE DE ÁNGULO, PTR Y PLACA A-36; INCLUYE: MATERIALES, DESPERDICIOS, MANO DE OBRA, HERRAMIENTA Y EQUIPO. UNA MANO DE PRIMARIO ANTICORROSIVO DE TALLER. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PTR DIF. MEDIDAS | PTR DIF. MEDIDAS | KG | 0.016400 | $13.60 | $0.22 |
| PERFIL ZINTRO-07 | ANGULO DE FIERRO DE 1 1/2 * 3/16" | KG | 0.654500 | $16.67 | $10.91 |
| PLACA A-36 | PLACA A-36 | KG | 0.414000 | $13.35 | $5.53 |
| GAS P/ CORTES | GAS P/ CORTES | KG | 0.009000 | $8.70 | $0.08 |
| OXIGENO | OXIGENO | M3 | 0.013000 | $19.00 | $0.25 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.026150 | $35.00 | $0.92 |
| DISCO ABRASIVO | DISCO ABRASIVO | PZA | 0.002200 | $45.00 | $0.10 |
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.007849 | $0.00 | $0.00 |
| Suma de Material | $18.00 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.002000 | $711.63 | $1.42 |
| CUADRILLA N° 342 | 1 of.soldador + 1 ayudante E. | JOR | 0.002000 | $711.63 | $1.42 |
| CUADRILLA N° 343 | 1 of.montador + 4 ayudante A. | JOR | 0.002000 | $1,363.22 | $2.73 |
| Suma de Mano de Obra | $5.57 | ||||
| Equipo | |||||
| EQUIPO DE CORTE | Equipo de corte de oxi-butano | HR | 0.013880 | $9.56 | $0.13 |
| ESMERILADORA | Esmeriladora | HR | 0.028440 | $2.88 | $0.08 |
| SOLDADORA | Soldadora Miller Mod. S64 | HR | 0.011440 | $12.48 | $0.14 |
| GRUA | Grua de 20 ton. | HR | 0.003681 | $378.31 | $1.39 |
| Suma de Equipo | $1.75 | ||||
| Auxiliar | |||||
| PRIMARIO ANTICORR | PRIMARIO ANTICORROSIVO | M2 | 0.020000 | $36.96 | $0.74 |
| Suma de Auxiliar | $0.74 | ||||
| Costo Directo | $26.06 |