| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MAMP-01 | SUMINISTRO Y COLOCACION DE MAMPARAS DE ACERO INOXIDABLE PUERTA DE 0.60*1.50 FABRICADAS CON BASTIDOR DE PERFIL TUBULAR GALVANIZADO, HONEY COMB, LAMINA DEACERO INOXIDABLE, MARCO PERIMETRAL DE ALUMINIO ANODIZADO COLOR NATURAL MATE INCLUYE CHAPA Y ACCESORIOS PARA SU COLOCACION | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAMPARA-01 | MAMPARAS DE ACERO INOXIDABLE PUERTA DE 0.60*1.50 FABRICADAS CON BASTIDOR DE PERFIL TUBULAR GALVANIZADO, HONEY COMB, LAMINA DEACERO INOXIDABLE, MARCO PERIMETRAL DE ALUMINIO ANODIZADO COLOR NATURAL MATE INCLUYE CHAPA Y ACCESORIOS | PZA | 1.000000 | $1,575.00 | $1,575.00 |
| MAMPARA-01 | MAMPARAS DE ACERO INOXIDABLE PUERTA DE 0.60*1.50 FABRICADAS CON BASTIDOR DE PERFIL TUBULAR GALVANIZADO, HONEY COMB, LAMINA DEACERO INOXIDABLE, MARCO PERIMETRAL DE ALUMINIO ANODIZADO COLOR NATURAL MATE INCLUYE CHAPA Y ACCESORIOS | PZA | 1.000000 | $1,575.00 | $1,575.00 |
| MAMPARA-01 | MAMPARAS DE ACERO INOXIDABLE PUERTA DE 0.60*1.50 FABRICADAS CON BASTIDOR DE PERFIL TUBULAR GALVANIZADO, HONEY COMB, LAMINA DEACERO INOXIDABLE, MARCO PERIMETRAL DE ALUMINIO ANODIZADO COLOR NATURAL MATE INCLUYE CHAPA Y ACCESORIOS | PZA | 1.000000 | $1,575.00 | $1,575.00 |
| MAMPARA-02. | CHAPA PARA PUERTA | PZA | 1.000000 | $210.00 | $210.00 |
| MAMPARA-02. | CHAPA PARA PUERTA | PZA | 1.000000 | $210.00 | $210.00 |
| MAMPARA-02. | CHAPA PARA PUERTA | PZA | 1.000000 | $210.00 | $210.00 |
| FLETE | FLETE | FLETE | 0.034675 | $10,000.00 | $346.75 |
| FLETE | FLETE | FLETE | 0.034675 | $10,000.00 | $346.75 |
| FLETE | FLETE | FLETE | 0.034675 | $10,000.00 | $346.75 |
| Suma de Material | $6,395.25 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 343 | 1 of.montador + 4 ayudante A. | JOR | 0.220067 | $1,363.22 | $300.00 |
| CUADRILLA N° 343 | 1 of.montador + 4 ayudante A. | JOR | 0.220067 | $1,363.22 | $300.00 |
| CUADRILLA N° 343 | 1 of.montador + 4 ayudante A. | JOR | 0.220067 | $1,363.22 | $300.00 |
| Suma de Mano de Obra | $900.00 | ||||
| Costo Directo | $7,295.25 |