| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HERR-36 | SUMINISTRO Y COLOCACION DE PORTON PLEGADIZO DE A PROYECTO | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-MOTO-PTR-01 | PTR DE DIFERENTES MEDIDAS | KG | 3,500.000000 | $16.00 | $56,000.00 |
| CHE-ESTRUC-16 | PLACA DE ACERO A-36 DE 3/16" | kg | 350.000000 | $13.59 | $4,756.50 |
| CHE-TAQUETE HILT-3/8 | TAQUETES HILTI DE 3/8 | PZA | 40.000000 | $20.00 | $800.00 |
| CHE-COMBUST-06 | GAS MARCA VERAGAS | KG | 150.000000 | $8.70 | $1,305.00 |
| CHE-COMBUST-05 | OXIGENO | M3 | 150.000000 | $52.00 | $7,800.00 |
| CHE-ESTRUC-01 | SOLDADURA E-7018 DE 1/8" | KG | 60.000000 | $52.00 | $3,120.00 |
| CHE-ESTRUCMET-13 | DISCO ABRASIVO | PZA | 10.000000 | $45.00 | $450.00 |
| CHE-FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.500000 | $0.00 | $0.00 |
| Suma de Material | $74,231.50 | ||||
| Mano de Obra | |||||
| CUA-CUADRILLA NO-10 | Cuadrilla de 1 of.pailero + 1 ayudante E. | jor | 10.000000 | $1,224.89 | $12,248.90 |
| CUA-CUADRILLA NO-11 | Cuadrilla 1 of.soldador + 1 ayudante E. | jor | 10.000000 | $1,224.89 | $12,248.90 |
| CUA-CUADRILLA NO-12 | Cuadrilla de 1 of.montador + 4 ayudante A. | jor | 10.000000 | $2,431.02 | $24,310.20 |
| Suma de Mano de Obra | $48,808.00 | ||||
| Equipo | |||||
| CHE-EQUIPO-027 | Equipo de corte de oxi-butano | HR | 0.080000 | $8.47 | $0.68 |
| CHE-EQUIPO-034 | Esmeriladora | HR | 0.123400 | $2.88 | $0.36 |
| CHE-EQUIPO-002 | SOLDADORA LINCOLN SAE 300 AMP. K 1277 MOT. PERKINS 4236, 4 CIL. 60 HP. 1600 R.P.M. | HR | 0.067000 | $8.70 | $0.58 |
| Suma de Equipo | $1.62 | ||||
| Auxiliar | |||||
| PRIMARIO ANTICORR | PRIMARIO ANTICORROSIVO | M2 | 1.000000 | $49.09 | $49.09 |
| PINTUR-ESMALTE | APLICACION DE PINTURA DE ESMALTE COMEX 100.00 | M2 | 1.000000 | $123.33 | $123.33 |
| Suma de Auxiliar | $172.42 | ||||
| Costo Directo | $123,213.54 |